4130 W 63RD ST 90043

Certificate Information: 4130 W 63RD ST 90043

Application / Permit
22014-10000-03543
Plan Check / Job No.
B22LA13799
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE INTO ADU WITH ADDITION PER ORDINANCE AND LAMC 12.22 A33 (c)&(d).
Permit Issued
Issued on 10/13/2022
Issuing Office
Valley
Current Status
Permit Closed on 2/13/2024
Certificate of Occupancy
Permit Closed More Information

Permit Application Status History

Submitted 7/14/2022 APPLICANT
Assigned to Plan Check Engineer 7/18/2022 ZAW HAN
Corrections Issued 7/21/2022 ZAW HAN
Plan Check Approved 10/6/2022 RICARDO RAMIREZ
Issued 10/13/2022 APPLICANT
Permit Closed 11/30/2023 JOHN PARKER
Refund in Progress 12/6/2023 SELENIA GARCIA
Refund Denied 2/13/2024 EMILY HU
Permit Closed 2/13/2024 EMILY HU

Permit Application Clearance Information

Address approval Cleared 8/2/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 8/2/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/4/2022 JEANIE LAM
Sewer availability Cleared 8/4/2022 JEANIE LAM
Construction near power lines Cleared 9/29/2022 RIDWAN HARDY
Grading Pre-Inspection Cleared 10/6/2022 RICARDO RAMIREZ

Contact Information

Contractor Creative Remodeling #1 Inc; Lic. No.: 1014676-B 6120 SAINT CLAIRE AVENUE      VALLEY GLEN, CA 91606
Engineer Mchantaf,, Kamal Beshara; Lic. No.: C51050 23315 SARATOGA SPRINGS PL      MURRIETA, CA 92562

Inspector Information

JOHN PARKER, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MICHAEL SERETTI, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
HECTOR RODRIGUEZ, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
BRUCE TODD, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
JAVIER RAMOS SR, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MARIAN PODPORA, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/24/2022 Approved RYAN SALAZAR
Footing/Foundation/Slab 10/31/2022 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 11/9/2022 Corrections Issued DANIEL GONZALEZ
Pre-Inspection 12/20/2022 Partial Inspection DANIEL GONZALEZ
Pre-Inspection 7/13/2023 No Access for Inspection DANIEL GONZALEZ
Pre-Inspection 8/1/2023 No Access for Inspection JOHN PARKER
Pre-Inspection 8/3/2023 Partial Inspection DANIEL GONZALEZ
Footing/Foundation/Slab 11/30/2023 Permit Closed JOHN PARKER