3428 1/2 E ISABEL DR 90065

Certificate Information: 3428 1/2 E ISABEL DR 90065

Application / Permit
22014-10000-03519
Plan Check / Job No.
B22LA13700
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* CONVERT (E) DETACHED 1-CAR GARAGE (272 SF) TO ADU AND ADDITION (459 SF) PER LAMC 12.22A.33(c)-(d).
Permit Issued
Issued on 9/22/2022
Issuing Office
Current Status
CofO Issued on 3/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2022 APPLICANT
Assigned to Plan Check Engineer 7/22/2022 VIVIAN LAO
Corrections Issued 7/25/2022 VIVIAN LAO
Applicant returned to address corrections 9/16/2022 VIVIAN LAO
Plan Check Approved 9/22/2022 VIVIAN LAO
Issued 9/22/2022 APPLICANT
CofO in Progress 3/6/2023 OSVALDO PARAMO
CofO in Progress 3/6/2023 OSVALDO PARAMO
Permit Finaled 3/15/2023 DEROLD HAUFF
CofO Issued 3/15/2023 DEROLD HAUFF
Permit Finaled 3/15/2023 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 7/26/2022 ISMAEL HERNANDEZ
Address approval Cleared 7/29/2022 STEVE MELGAR
Specific Plan Cleared 8/8/2022 PABLO ESTRADA
Low Impact Development Cleared 9/6/2022 ROGELIO CORTES
GPI Written Notices Cleared 9/8/2022 VIVIAN LAO
Grading Pre-Inspection Cleared 9/8/2022 VIVIAN LAO
Roof/Waste drainage to street Cleared 9/8/2022 STEVE MELGAR
Miscellaneous Cleared 9/13/2022 ALBERT TAM
Eng Process Fee Ord 176,300 Cleared 9/19/2022 STEVE MELGAR
Sewer availability Cleared 9/19/2022 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Barragan,, Pedro; Lic. No.: C90531 329 N HUBBARD AVE      SAN FERNANDO, CA 91340

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/12/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 10/19/2022 Approved OSVALDO PARAMO
ELECTRICAL-Rough 11/29/2022 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 11/29/2022 Partial Approval OSVALDO PARAMO
Green Building Rough 11/29/2022 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 11/29/2022 Not Ready for Inspection OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 12/5/2022 Corrections Issued OSVALDO PARAMO
Wood Frame 12/5/2022 Corrections Issued OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 12/8/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 12/13/2022 Approved OSVALDO PARAMO
Green Building Rough 12/13/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 12/13/2022 Partial Approval OSVALDO PARAMO
Insulation 12/16/2022 Approved OSVALDO PARAMO
Drywall Nailing 12/21/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 12/21/2022 Approved OSVALDO PARAMO
Underground Mechanical 1/24/2023 Partial Approval OSVALDO PARAMO
Final 2/23/2023 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 2/23/2023 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/23/2023 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 2/23/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 2/28/2023 Approved OSVALDO PARAMO
Final 2/28/2023 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 2/28/2023 SGSOV Approved OSVALDO PARAMO
Final 3/3/2023 OK to Issue CofO OSVALDO PARAMO