7832 S CROYDON AVE 90045

Certificate Information: 7832 S CROYDON AVE 90045

Application / Permit
22014-10000-03479
Plan Check / Job No.
B22LA13604
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan ADDITION 959 SF TO SINGLE FAMILY DWELLING INTERIOR REMODEL
Permit Issued
Issued on 12/1/2022
Issuing Office
Current Status
CofO Issued on 11/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2022 APPLICANT
Assigned to Plan Check Engineer 8/11/2022 CARLOS MONTES
Corrections Issued 8/17/2022 CARLOS MONTES
Quality Review Completed 8/18/2022 GARO TELMI
Plan Check Approved 10/26/2022 CARLOS MONTES
Issued 12/1/2022 APPLICANT
CofO in Progress 11/20/2025 JESUS PINEDA
Permit Finaled 11/21/2025 RICHARD STEINBACH
CofO Issued 11/21/2025 RICHARD STEINBACH
Permit Finaled 11/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/26/2022 ANTHONY MAINEZ
Sewer availability Cleared 9/26/2022 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 9/29/2022 KIRK LINKLATER
Low Impact Development Cleared 10/5/2022 ORVAL HERNANDEZ-MARCI
GPI Written Notices Cleared 10/7/2022 CARLOS MONTES
Roof/Waste drainage to street Cleared 10/12/2022 ANTHONY MAINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Nagovitsyn,, Evgeny; Lic. No.: C93527 17436 ARMINTA ST      NORTHRIDGE, CA 91325

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/27/2023 Conditional Approval BOBBY KEY
Special/Order Compliance 4/27/2023 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 5/18/2023 Approved BOBBY KEY
Underground Mechanical 5/18/2023 Partial Approval BOBBY KEY
Wood Frame 5/18/2023 Partial Approval BOBBY KEY
Deputy Wood Construction 6/20/2023 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval BOBBY KEY
ELECTRICAL-Rough 6/29/2023 Not Ready for Inspection BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/29/2023 Not Ready for Inspection BOBBY KEY
HVAC-Rough 6/29/2023 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 6/29/2023 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 7/5/2023 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Approved BOBBY KEY
ELECTRICAL-Rough 7/11/2023 Not Ready for Inspection BOBBY KEY
HVAC-Rough 7/11/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 7/11/2023 Approved BOBBY KEY
ELECTRICAL-Rough 7/25/2023 Approved BOBBY KEY
HVAC-Rough 7/25/2023 Approved BOBBY KEY
Interior/Exterior Lathing 7/25/2023 Partial Approval BOBBY KEY
Insulation 9/11/2023 Approved TEMISTOCLES CAAL
Shower Pan 9/11/2023 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 9/21/2023 Approved BOBBY KEY
Drywall Nailing 9/21/2023 Approved BOBBY KEY
Green Building Rough 9/21/2023 Approved BOBBY KEY
Verify Sprinkler Sign Off 9/21/2023 Approved BOBBY KEY
Special/Order Compliance 5/2/2024 Corrections Issued BOBBY KEY
Special/Order Compliance 5/6/2024 Partial Inspection BOBBY KEY
ELECTRICAL-Final 4/14/2025 Corrections Issued JESUS PINEDA
Gas Test 4/14/2025 Approved JESUS PINEDA
PLUMBING-Final 4/14/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Final 6/20/2025 Corrections Issued BOBBY KEY
Final 6/20/2025 Corrections Issued BOBBY KEY
Gas Test 6/20/2025 Corrections Issued BOBBY KEY
Green Building Final 6/20/2025 Not Ready for Inspection BOBBY KEY
HVAC-Final 6/20/2025 Corrections Issued BOBBY KEY
PLUMBING-Final 6/20/2025 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 6/20/2025 SGSOV Not Ready BOBBY KEY
Smoke Detectors 6/20/2025 Approved BOBBY KEY
Final 7/3/2025 Corrections Issued RUBEN RIVAS
Green Building Final 7/3/2025 Not Ready for Inspection RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 7/3/2025 SGSOV Not Ready RUBEN RIVAS
ELECTRICAL-Final 10/29/2025 Approved JESUS PINEDA
Final 10/29/2025 Not Ready for Inspection JESUS PINEDA
Green Building Final 10/29/2025 Approved JESUS PINEDA
HVAC-Final 10/29/2025 Approved JESUS PINEDA
PLUMBING-Final 10/29/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 10/29/2025 SGSOV Approved JESUS PINEDA
Service/Power Release 10/29/2025 Approved JESUS PINEDA
Final 11/20/2025 OK to Issue CofO JESUS PINEDA