7832 S CROYDON AVE 90045
Certificate Information: 7832 S CROYDON AVE 90045
- Application / Permit
- 22014-10000-03479
- Plan Check / Job No.
- B22LA13604
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan ADDITION 959 SF TO SINGLE FAMILY DWELLING INTERIOR REMODEL
- Permit Issued
- Issued on 12/1/2022
- Issuing Office
- Current Status
- CofO Issued on 11/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2022 | CARLOS MONTES |
| Corrections Issued | 8/17/2022 | CARLOS MONTES |
| Quality Review Completed | 8/18/2022 | GARO TELMI |
| Plan Check Approved | 10/26/2022 | CARLOS MONTES |
| Issued | 12/1/2022 | APPLICANT |
| CofO in Progress | 11/20/2025 | JESUS PINEDA |
| Permit Finaled | 11/21/2025 | RICHARD STEINBACH |
| CofO Issued | 11/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2022 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 9/26/2022 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 9/29/2022 | KIRK LINKLATER |
| Low Impact Development | Cleared | 10/5/2022 | ORVAL HERNANDEZ-MARCI |
| GPI Written Notices | Cleared | 10/7/2022 | CARLOS MONTES |
| Roof/Waste drainage to street | Cleared | 10/12/2022 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nagovitsyn,, Evgeny; Lic. No.: C93527 | 17436 ARMINTA ST NORTHRIDGE, CA 91325 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/27/2023 | Conditional Approval | BOBBY KEY |
| Special/Order Compliance | 4/27/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 5/18/2023 | Approved | BOBBY KEY |
| Underground Mechanical | 5/18/2023 | Partial Approval | BOBBY KEY |
| Wood Frame | 5/18/2023 | Partial Approval | BOBBY KEY |
| Deputy Wood Construction | 6/20/2023 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 6/29/2023 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 6/29/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 6/29/2023 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 7/5/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 7/11/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 7/11/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 7/11/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 7/25/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 7/25/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 7/25/2023 | Partial Approval | BOBBY KEY |
| Insulation | 9/11/2023 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 9/11/2023 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 9/21/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 9/21/2023 | Approved | BOBBY KEY |
| Green Building Rough | 9/21/2023 | Approved | BOBBY KEY |
| Verify Sprinkler Sign Off | 9/21/2023 | Approved | BOBBY KEY |
| Special/Order Compliance | 5/2/2024 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 5/6/2024 | Partial Inspection | BOBBY KEY |
| ELECTRICAL-Final | 4/14/2025 | Corrections Issued | JESUS PINEDA |
| Gas Test | 4/14/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 4/14/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 6/20/2025 | Corrections Issued | BOBBY KEY |
| Final | 6/20/2025 | Corrections Issued | BOBBY KEY |
| Gas Test | 6/20/2025 | Corrections Issued | BOBBY KEY |
| Green Building Final | 6/20/2025 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 6/20/2025 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 6/20/2025 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/20/2025 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 6/20/2025 | Approved | BOBBY KEY |
| Final | 7/3/2025 | Corrections Issued | RUBEN RIVAS |
| Green Building Final | 7/3/2025 | Not Ready for Inspection | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 7/3/2025 | SGSOV Not Ready | RUBEN RIVAS |
| ELECTRICAL-Final | 10/29/2025 | Approved | JESUS PINEDA |
| Final | 10/29/2025 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Final | 10/29/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 10/29/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 10/29/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 10/29/2025 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 10/29/2025 | Approved | JESUS PINEDA |
| Final | 11/20/2025 | OK to Issue CofO | JESUS PINEDA |