7907 N LOUISE AVE 91325

Certificate Information: 7907 N LOUISE AVE 91325

Application / Permit
22014-10000-03448
Plan Check / Job No.
B22LA13479
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
A NEW SECOND STORY ADDITION AND INTERIOR STR. REMODEL TO EXISITING SINGLE FAMILY RESIDENCE. NFPA 13D FIRE SPRINKLERS PROVIDED THROUGHOUT
Permit Issued
Issued on 6/27/2023
Issuing Office
Current Status
CofO Issued on 1/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2022 APPLICANT
Assigned to Plan Check Engineer 8/4/2022 MAHNAZ NOURHASHEMI
Corrections Issued 8/11/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 8/18/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 8/23/2022 APPLICANT
Applicant returned to address corrections 3/1/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 3/3/2023 MAHNAZ NOURHASHEMI
Issued 6/27/2023 APPLICANT
CofO in Progress 1/17/2025 GAREN HAYRAPETYAN
CofO Issued 1/24/2025 RUBEN SALAS
Permit Finaled 1/24/2025 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development Cleared 2/13/2023 ROGELIO CORTES
Eng Process Fee Ord 176,300 Cleared 3/3/2023 RYAN KIM
Roof/Waste drainage to street Cleared 3/3/2023 RYAN KIM
Sewer availability Cleared 3/3/2023 RYAN KIM

Contact Information

Contractor Aten Enterprises; Lic. No.: 782418-B 900 WHITE KNOLL      LOS ANGELES, CA 90012
Engineer Garcia,, Lionel Jesus; Lic. No.: S4653 24702 NARBONNE AVE      LOMITA, CA 90717

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/14/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/18/2023 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 9/28/2023 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 10/16/2023 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 10/19/2023 Approved RAUL OLAGI
PLUMBING-Rough 10/19/2023 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 1/17/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 1/30/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 2/2/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 2/2/2024 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 2/9/2024 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/9/2024 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 3/7/2024 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 3/12/2024 Not Ready for Inspection RAUL OLAGI
Interior/Exterior Lathing 3/12/2024 Partial Approval RAUL OLAGI
Interior/Exterior Lathing 4/10/2024 Approved RAUL OLAGI
Shower Pan 4/10/2024 Approved RAUL OLAGI
Insulation 4/24/2024 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 5/8/2024 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 5/8/2024 Approved RAUL OLAGI
HVAC-Rough 5/8/2024 Approved RAUL OLAGI
Insulation 5/8/2024 Approved RAUL OLAGI
PLUMBING-Rough 5/8/2024 Approved RAUL OLAGI
Drywall Nailing 6/3/2024 Not Ready for Inspection SALVADOR MARTINEZ
Drywall Nailing 6/11/2024 Partial Approval RAUL OLAGI
Drywall Nailing 6/20/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 12/26/2024 Not Ready for Inspection GAREN HAYRAPETYAN
Final 12/26/2024 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 12/26/2024 Not Ready for Inspection GAREN HAYRAPETYAN
Green Building Rough 12/26/2024 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 12/26/2024 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 12/26/2024 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 1/13/2025 Approved GAREN HAYRAPETYAN
Final 1/13/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Green Building Final 1/13/2025 Corrections Issued GAREN HAYRAPETYAN
Final 1/17/2025 OK to Issue CofO GAREN HAYRAPETYAN
Green Building Final 1/17/2025 Approved GAREN HAYRAPETYAN