1598 N SORRENTO DR 90272
Certificate Information: 1598 N SORRENTO DR 90272
- Application / Permit
- 22014-10000-03442
- Plan Check / Job No.
- B22LA13463
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SFD AND ADDITION TO SFD TO CREATE AN ATTACHED ADU PER ORDINANCE
- Permit Issued
- Issued on 2/9/2023
- Issuing Office
- Current Status
- CofO Issued on 10/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | CARLOS MONTES |
| Corrections Issued | 7/24/2022 | CARLOS MONTES |
| Quality Review Completed | 7/27/2022 | GARO TELMI |
| Applicant returned to address corrections | 11/9/2022 | CARLOS MONTES |
| Plan Check Approved | 1/10/2023 | CARLOS MONTES |
| Issued | 2/9/2023 | APPLICANT |
| CofO in Progress | 9/6/2024 | KEVIN SARGSYAN |
| Permit Finaled | 10/31/2024 | RICHARD STEINBACH |
| CofO Issued | 10/31/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/31/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/23/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 8/30/2022 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 9/6/2022 | CATHERINE ADROVER |
| Hydrant and Access approval | Cleared | 9/28/2022 | KURT CORRAL |
| GPI Written Notices | Cleared | 1/10/2023 | CARLOS MONTES |
| Grading Pre-Inspection | Cleared | 1/10/2023 | CARLOS MONTES |
Contact Information
| Contractor | D K R Construction Inc; Lic. No.: 1070450-B | , |
| Engineer | Resnick,, Bruce Daniel; Lic. No.: S3293 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/15/2023 | Approved | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 6/28/2023 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 6/28/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Piling/Pier/Caisson | 6/28/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 7/3/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2023 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/12/2023 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2023 | Partial Approval | KEVIN SARGSYAN |
| Special/Order Compliance | 10/12/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/13/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/17/2023 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/3/2023 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2023 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 11/3/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/3/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/8/2023 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 11/8/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/8/2023 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 12/1/2023 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 12/1/2023 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/1/2023 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 12/7/2023 | Approved | KEVIN SARGSYAN |
| Shower Pan | 12/12/2023 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 12/13/2023 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 12/14/2023 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 7/17/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 7/17/2024 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/17/2024 | Approved | KEVIN SARGSYAN |
| Green Building Final | 7/17/2024 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 7/17/2024 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 7/17/2024 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 7/17/2024 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 7/17/2024 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/3/2024 | Partial Inspection | HERBERT GIRON |
| Final | 9/3/2024 | Partial Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/6/2024 | Approved | KEVIN SARGSYAN |
| Final | 9/6/2024 | OK to Issue CofO | KEVIN SARGSYAN |