1598 N SORRENTO DR 90272

Certificate Information: 1598 N SORRENTO DR 90272

Application / Permit
22014-10000-03442
Plan Check / Job No.
B22LA13463
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SFD AND ADDITION TO SFD TO CREATE AN ATTACHED ADU PER ORDINANCE
Permit Issued
Issued on 2/9/2023
Issuing Office
Current Status
CofO Issued on 10/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2022 APPLICANT
Assigned to Plan Check Engineer 7/21/2022 CARLOS MONTES
Corrections Issued 7/24/2022 CARLOS MONTES
Quality Review Completed 7/27/2022 GARO TELMI
Applicant returned to address corrections 11/9/2022 CARLOS MONTES
Plan Check Approved 1/10/2023 CARLOS MONTES
Issued 2/9/2023 APPLICANT
CofO in Progress 9/6/2024 KEVIN SARGSYAN
Permit Finaled 10/31/2024 RICHARD STEINBACH
CofO Issued 10/31/2024 RICHARD STEINBACH
Permit Finaled 10/31/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/23/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 8/30/2022 CATHERINE ADROVER
Sewer availability Cleared 8/30/2022 CATHERINE ADROVER
Roof/Waste drainage to street Cleared 9/6/2022 CATHERINE ADROVER
Hydrant and Access approval Cleared 9/28/2022 KURT CORRAL
GPI Written Notices Cleared 1/10/2023 CARLOS MONTES
Grading Pre-Inspection Cleared 1/10/2023 CARLOS MONTES

Contact Information

Contractor D K R Construction Inc; Lic. No.: 1070450-B       ,
Engineer Resnick,, Bruce Daniel; Lic. No.: S3293 1927 PONTIUS AVE      LOS ANGELES, CA 90025

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/15/2023 Approved CARLOS MATAMOROS
Deputy Drilled-In Anchors 6/28/2023 No Access for Inspection KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 6/28/2023 Corrections Issued OGANES TARAKHCHYAN
Piling/Pier/Caisson 6/28/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 7/3/2023 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 8/21/2023 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 10/12/2023 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 10/12/2023 Partial Approval KEVIN SARGSYAN
Special/Order Compliance 10/12/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 10/13/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 10/17/2023 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 11/3/2023 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/3/2023 Approved KEVIN SARGSYAN
HVAC-Rough 11/3/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 11/3/2023 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 11/8/2023 Approved KEVIN SARGSYAN
HVAC-Rough 11/8/2023 Approved KEVIN SARGSYAN
PLUMBING-Rough 11/8/2023 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 12/1/2023 Corrections Issued KEVIN SARGSYAN
Green Building Rough 12/1/2023 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 12/1/2023 Partial Approval KEVIN SARGSYAN
Insulation 12/7/2023 Approved KEVIN SARGSYAN
Shower Pan 12/12/2023 Approved KEVIN SARGSYAN
Drywall Nailing 12/13/2023 Approved BEN MOLSTAD
Interior/Exterior Lathing 12/14/2023 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 7/17/2024 Not Ready for Inspection KEVIN SARGSYAN
Final 7/17/2024 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 7/17/2024 Approved KEVIN SARGSYAN
Green Building Final 7/17/2024 Approved KEVIN SARGSYAN
HVAC-Final 7/17/2024 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 7/17/2024 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 7/17/2024 Approved KEVIN SARGSYAN
Verify Sprinkler Sign Off 7/17/2024 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 9/3/2024 Partial Inspection HERBERT GIRON
Final 9/3/2024 Partial Inspection HERBERT GIRON
BUILDING-Rough-Frame 9/6/2024 Approved KEVIN SARGSYAN
Final 9/6/2024 OK to Issue CofO KEVIN SARGSYAN