3661 E GILLIG AVE 90031
Certificate Information: 3661 E GILLIG AVE 90031
- Application / Permit
- 22014-10000-03427
- Plan Check / Job No.
- B22LA13334
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: ADDITION TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 7/31/2023
- Issuing Office
- Current Status
- CofO Issued on 10/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2022 | JOE VO |
| Corrections Issued | 7/31/2022 | JOE VO |
| Applicant returned to address corrections | 9/7/2022 | JOE VO |
| Plan Check Approved | 7/23/2023 | DANIEL YIP |
| Issued | 7/31/2023 | APPLICANT |
| CofO in Progress | 10/9/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 10/11/2025 | DEROLD HAUFF |
| CofO Issued | 10/11/2025 | DEROLD HAUFF |
| Permit Finaled | 10/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/16/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 8/16/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 8/16/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 8/16/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 8/16/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 8/16/2022 | JEANIE LAM |
| Sewer availability | Cleared | 8/16/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2022 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 9/25/2022 | RUEL COLE |
| "D" conditions | Cleared | 3/28/2023 | ANACANY HURTADO |
| "Q" conditions | Cleared | 3/28/2023 | ANACANY HURTADO |
| Grading Pre-Inspection | Cleared | 5/2/2023 | SERGIO VALENZUELA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/27/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 7/17/2025 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 7/21/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2025 | Partial Approval | REGINA MENDEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/1/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 8/1/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 8/1/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 8/1/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/1/2025 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 8/5/2025 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 8/5/2025 | Approved | GEM DE OCAMPO |
| Drywall Nailing | 8/7/2025 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 8/7/2025 | Approved | GEM DE OCAMPO |
| BUILDING-Rough-Frame | 9/24/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 9/24/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 9/24/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 9/24/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 9/24/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 9/24/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 9/24/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 10/6/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 10/6/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 10/9/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |