15911 S ORCHARD AVE 90247

Certificate Information: 15911 S ORCHARD AVE 90247

Application / Permit
22014-10000-03425
Plan Check / Job No.
B22LA13332
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 2/16/2023
Issuing Office
Current Status
CofO Issued on 12/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2022 APPLICANT
Assigned to Plan Check Engineer 7/18/2022 DANIEL YIP
Corrections Issued 7/19/2022 DANIEL YIP
Applicant returned to address corrections 8/15/2022 DANIEL YIP
Applicant returned to address corrections 8/25/2022 DANIEL YIP
Applicant returned to address corrections 8/26/2022 DANIEL YIP
Plan Check Approved 2/9/2023 DANIEL YIP
Issued 2/16/2023 APPLICANT
CofO in Progress 12/17/2025 BEN MOLSTAD
Permit Finaled 12/18/2025 ANSON MAGLASANG
Permit Finaled 12/18/2025 ANSON MAGLASANG
CofO Issued 12/18/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 7/25/2022 ERIK BEASLEY
Roof/Waste drainage to street Cleared 7/27/2022 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 8/11/2022 JOSE HERNANDEZ
Sewer availability Cleared 8/11/2022 JOSE HERNANDEZ
Low Impact Development Cleared 11/30/2022 DEBORA LEITE

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/25/2023 Partial Approval JAMES CHAVEZ
Pre-Inspection 7/17/2023 Partial Inspection JAMES CHAVEZ
ELECTRICAL-Rough 11/15/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 11/15/2023 Corrections Issued JAMES CHAVEZ
HVAC-Rough 11/15/2023 Corrections Issued JAMES CHAVEZ
MERV13>=Rough 11/15/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 11/15/2023 Approved JAMES CHAVEZ
Verify Sprinkler Sign Off 11/15/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 11/20/2023 Partial Approval JAMES CHAVEZ
Green Building Rough 11/20/2023 Not Ready for Inspection JAMES CHAVEZ
HVAC-Rough 11/20/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 11/28/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 11/28/2023 Partial Approval JAMES CHAVEZ
Green Building Rough 11/28/2023 Approved JAMES CHAVEZ
Insulation 11/30/2023 Corrections Issued EUGENE CASSIDY
Insulation 12/7/2023 Approved JAMES CHAVEZ
Sewer 12/7/2023 Approved JAMES CHAVEZ
Drywall Nailing 12/19/2023 Approved JOHN KLARIN
Final 2/5/2025 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 2/5/2025 Approved BEN MOLSTAD
Green Building Final 2/5/2025 Not Ready for Inspection BEN MOLSTAD
MERV13>=Final 2/5/2025 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 2/5/2025 SGSOV Not Ready BEN MOLSTAD
Service/Power Release 2/5/2025 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 2/5/2025 Not Ready for Inspection BEN MOLSTAD
Final 3/11/2025 Corrections Issued JOSEPH MCGARRY
Green Building Final 3/11/2025 Approved JOSEPH MCGARRY
MERV13>=Final 3/11/2025 Not Ready for Inspection JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 3/11/2025 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 3/11/2025 Not Ready for Inspection JOSEPH MCGARRY
Smoke Detectors 3/11/2025 Not Ready for Inspection JOSEPH MCGARRY
Final 5/6/2025 Corrections Issued BEN MOLSTAD
HVAC-Final 5/6/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Final 5/6/2025 Not Ready for Inspection BEN MOLSTAD
Final 6/17/2025 Corrections Issued BEN MOLSTAD
MERV13>=Final 6/17/2025 Approved BEN MOLSTAD
Service/Power Release 6/17/2025 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 6/17/2025 Approved BEN MOLSTAD
Final 6/23/2025 Not Ready for Inspection BEN MOLSTAD
Service/Power Release 6/23/2025 Not Ready for Inspection BEN MOLSTAD
Final 6/26/2025 Corrections Issued BEN MOLSTAD
Service/Power Release 6/26/2025 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Final 7/2/2025 Approved BEN MOLSTAD
Final 7/2/2025 Not Ready for Inspection BEN MOLSTAD
HVAC-Final 7/2/2025 Approved BEN MOLSTAD
PLUMBING-Final 7/2/2025 Approved BEN MOLSTAD
Service/Power Release 7/2/2025 Approved BEN MOLSTAD
Final 7/3/2025 Corrections Issued BEN MOLSTAD
Final 12/4/2025 Not Ready for Inspection BEN MOLSTAD
Final 12/10/2025 Corrections Issued BEN MOLSTAD
Final 12/17/2025 OK to Issue CofO BEN MOLSTAD