5125 N ROCKLAND AVE 90041
Certificate Information: 5125 N ROCKLAND AVE 90041
- Application / Permit
- 22014-10000-03414
- Plan Check / Job No.
- B22LA13300
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND MAJOR REMODEL FOR EXISTING ONE STORY SINGLE FAMILY DWELLING PER ENGINEER DESIGN
- Permit Issued
- Issued on 8/2/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2022 | AUNG SOE |
| Corrections Issued | 7/13/2022 | AUNG SOE |
| Building Plans Picked Up | 7/19/2022 | APPLICANT |
| Plan Check Approved | 8/2/2022 | JOSEPH RAFOLS |
| Issued | 8/2/2022 | APPLICANT |
| CofO in Progress | 5/1/2023 | BRIAN SULLIVAN |
| CofO Issued | 5/3/2023 | DEROLD HAUFF |
| Permit Finaled | 5/3/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/30/2022 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 7/30/2022 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2022 | ADRIAN SANCHEZ |
| Grading Pre-Inspection | Cleared | 8/2/2022 | AUNG SOE |
Contact Information
| Contractor | Edesign & Building Inc; Lic. No.: 1092614-B | 3327 W BEVERLY BLVD MONTEBELLO, CA 90640 |
| Engineer | Mchantaf,, Kamal Beshara; Lic. No.: C51050 | 23315 SARATOGA SPRINGS PL MURRIETA, CA 92562 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/23/2022 | Corrections Issued | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 8/26/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/1/2022 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 9/1/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Deputy Wood Construction | 9/16/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/27/2022 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 9/27/2022 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Rough | 9/27/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 9/27/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 10/4/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 10/4/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 10/4/2022 | Approved | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 11/18/2022 | Conditional Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/29/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 11/29/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 12/6/2022 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 12/14/2022 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 12/22/2022 | Approved | CHARLES BOGHOSKHAN |
| Final | 3/30/2023 | No Access for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 3/30/2023 | Approved | CRAIG VAUGHAN |
| Green Building Final | 3/30/2023 | No Access for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 3/30/2023 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 3/30/2023 | No Access for Inspection | CRAIG VAUGHAN |
| Final | 4/24/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Gas Test | 4/24/2023 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 4/24/2023 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/24/2023 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 4/24/2023 | Approved | CRAIG VAUGHAN |
| Final | 4/28/2023 | OK to Issue CofO | BRIAN SULLIVAN |