5341-5343 E RAPHAEL ST 90042

Certificate Information: 5341-5343 E RAPHAEL ST 90042

Application / Permit
22014-10000-03396
Plan Check / Job No.
B22LA13245
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan - 1 STORY ADU ADDITION (582 SF) AND BALCONY REMODEL TO EXISTING 1 STORY SFD W GARAGE PER 12.22 A 33 C & E, SEE COMMENTS
Permit Issued
Issued on 8/4/2023
Issuing Office
Current Status
CofO Issued on 12/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2022 APPLICANT
Assigned to Plan Check Engineer 8/4/2022 STARR CHEN
Corrections Issued 8/9/2022 STARR CHEN
Quality Review Completed 8/18/2022 EUGENE BARBEAU
Applicant returned to address corrections 5/4/2023 STARR CHEN
Applicant returned to address corrections 5/12/2023 STARR CHEN
Plan Check Approved 8/3/2023 STARR CHEN
Issued 8/4/2023 APPLICANT
CofO in Progress 12/23/2024 THOMAS LOGRASSO
Permit Finaled 12/26/2024 DEROLD HAUFF
Permit Finaled 12/26/2024 DEROLD HAUFF
CofO Issued 12/26/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/22/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 8/22/2022 STEVE MELGAR
Sewer availability Cleared 8/22/2022 STEVE MELGAR
Street Frontage Cleared 8/22/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/23/2022 STEVE MELGAR
Hydrant and Access approval Cleared 9/30/2022 KURT CORRAL
HPOZ Cleared 11/1/2022 DEEPEAKA DHALIWAL
ZI Cleared 11/1/2022 DEEPEAKA DHALIWAL
Grading Pre-Inspection Cleared 8/3/2023 STARR CHEN

Contact Information

Architect Belak-Berger,, Charles Peter; Lic. No.: NA13657       ,
Contractor Owner-Builder       ,
Engineer Attaalla,, Sayed Ahmed; Lic. No.: S5339 11254 HANNUM AVE      CULVER CITY, CA 90230

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/15/2023 Partial Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 1/16/2024 Conditional Approval HAMIK HARTOUNIAN
Deputy Wood Construction 1/17/2024 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/23/2024 Partial Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 2/1/2024 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 2/7/2024 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/29/2024 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 2/29/2024 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/18/2024 Corrections Issued BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 4/18/2024 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 4/18/2024 Corrections Issued BRIAN SULLIVAN
Shower Pan 4/18/2024 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 4/23/2024 Approved LILIANA PORTILLO
HVAC-Rough 4/23/2024 Approved LILIANA PORTILLO
PLUMBING-Rough 4/23/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 4/26/2024 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 4/26/2024 Approved HAMIK HARTOUNIAN
Drywall Nailing 6/6/2024 Not Ready for Inspection THOMAS LOGRASSO
Drywall Nailing 6/17/2024 Corrections Issued ALIZAH MAYAGOITIA
Insulation 6/17/2024 Approved HAMIK HARTOUNIAN
Drywall Nailing 6/21/2024 Approved BRENDAN MORELLI
Final 11/12/2024 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 11/12/2024 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 11/12/2024 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 11/12/2024 Approved THOMAS LOGRASSO
Final 12/20/2024 OK to Issue CofO THOMAS LOGRASSO
Service/Power Release 12/20/2024 Approved THOMAS LOGRASSO