1424 1/2 N OGDEN DR 90046
Certificate Information: 1424 1/2 N OGDEN DR 90046
- Application / Permit
- 22014-10000-03392
- Plan Check / Job No.
- B22LA13244
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: EGRESS ADDITION TO (E) GARAGE AND CONVERT TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 11/22/2022
- Issuing Office
- Current Status
- CofO Issued on 3/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2022 | DANIEL YIP |
| Corrections Issued | 7/19/2022 | DANIEL YIP |
| Plan Check Approved | 10/12/2022 | DANIEL YIP |
| Issued | 11/22/2022 | APPLICANT |
| CofO in Progress | 2/7/2024 | BRIAN SULLIVAN |
| Permit Finaled | 3/29/2025 | DEROLD HAUFF |
| CofO Issued | 3/29/2025 | DEROLD HAUFF |
| Permit Finaled | 3/29/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 8/5/2022 | LAMBERT GIESSINGER |
| Address approval | Cleared | 8/22/2022 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 8/22/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2022 | WALLIE JONG |
| Sewer availability | Cleared | 8/24/2022 | WALLIE JONG |
| Construction near power lines | Cleared | 9/24/2022 | RIDWAN HARDY |
Contact Information
| Architect | , ; Lic. No.: C38799 | 12324 SARAH ST STUDIO CITY, CA 91604 |
| Contractor | Gruen Construction Co Inc; Lic. No.: 746376-B | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/13/2023 | Partial Approval | STUART CHAPMAN |
| Gas Test | 3/21/2023 | Partial Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 3/21/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Sewer | 3/21/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Sewer | 3/24/2023 | Approved | STUART CHAPMAN |
| Underground Mechanical | 3/24/2023 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 4/13/2023 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 5/1/2023 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 5/8/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/9/2023 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 5/9/2023 | Partial Approval | STUART CHAPMAN |
| Wood Frame | 6/13/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Shower Pan | 6/23/2023 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2023 | Corrections Issued | STUART CHAPMAN |
| Deputy Wood Construction | 7/12/2023 | Conditional Approval | STUART CHAPMAN |
| Drywall Nailing | 7/14/2023 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 7/21/2023 | Partial Approval | STUART CHAPMAN |
| Gas Test | 7/26/2023 | Conditional Approval | RAUL BARAJAS |
| PLUMBING-Rough | 7/26/2023 | Conditional Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 7/31/2023 | Approved | STUART CHAPMAN |
| HVAC-Rough | 7/31/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 7/31/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 8/1/2023 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 8/1/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Wood Frame | 8/1/2023 | Partial Approval | STUART CHAPMAN |
| Insulation | 8/3/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Insulation | 8/4/2023 | Approved | STUART CHAPMAN |
| Drywall Nailing | 8/9/2023 | Conditional Approval | STUART CHAPMAN |
| Green Building Rough | 8/9/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Interior/Exterior Lathing | 8/9/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Final | 1/12/2024 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 1/12/2024 | Corrections Issued | STUART CHAPMAN |
| Pool/Spa Cover | 1/12/2024 | Approved | STUART CHAPMAN |
| Smoke Detectors | 1/12/2024 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 1/16/2024 | Approved | STUART CHAPMAN |
| Drywall Nailing | 1/16/2024 | Approved | STUART CHAPMAN |
| Final | 1/16/2024 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 1/16/2024 | Approved | STUART CHAPMAN |
| Green Building Final | 1/16/2024 | Approved | STUART CHAPMAN |
| Green Building Rough | 1/16/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 1/16/2024 | Partial Approval | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 1/16/2024 | SGSOV Approved | STUART CHAPMAN |
| Final | 1/19/2024 | Corrections Issued | RAUL BARAJAS |
| Final | 1/25/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Final | 2/6/2024 | OK to Issue CofO | BRIAN SULLIVAN |