14308 W COLLINS ST 91401
Certificate Information: 14308 W COLLINS ST 91401
- Application / Permit
- 22014-10000-03332
- Plan Check / Job No.
- B22LA13019
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 1-STORY MASTER BEDROOM/CLOSET/BATHROOM AND LAUNDRY ROOM ADDITION TOWARD REAR OF (E) SFD.
- Permit Issued
- Issued on 8/5/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 7/15/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 7/21/2022 | APPLICANT |
| Plan Check Approved | 8/5/2022 | YAQUB MIRZA |
| Issued | 8/5/2022 | APPLICANT |
| CofO in Progress | 3/21/2023 | RYAN SALAZAR |
| CofO Issued | 4/11/2023 | MICHAEL SMITH |
| Permit Finaled | 4/11/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 7/25/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 7/25/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 7/25/2022 | JOSE DUARTE-DIAZ |
| Public Works-Open Permits | Cleared | 7/25/2022 | JOSE DUARTE-DIAZ |
| Public Works-Sewers | Cleared | 7/25/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Ind Construction Llc; Lic. No.: 937833-B | 16430 VENTURA BLVD STE 208 ENCINO, CA 91436 |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/15/2022 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 11/18/2022 | Approved | WILLIAM WREN |
| Wood Frame | 11/30/2022 | Partial Approval | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2022 | Partial Approval | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 12/14/2022 | Approved | RYAN SALAZAR |
| Deputy Wood Construction | 12/15/2022 | Conditional Approval | ROBERT GOLD |
| ELECTRICAL-Rough | 12/22/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/22/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/4/2023 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 1/4/2023 | Approved | MATTHEW NELSON |
| Green Building Rough | 1/4/2023 | Approved | MATTHEW NELSON |
| Shower Pan | 1/4/2023 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 1/9/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 1/9/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 1/12/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 1/12/2023 | Approved | JAVIER RAMOS JR |
| Final | 3/3/2023 | Corrections Issued | RYAN SALAZAR |
| Final | 3/22/2023 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 3/22/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 3/22/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 3/22/2023 | Approved | RYAN SALAZAR |