1270 N SUNSET PLAZA DR 90069

Certificate Information: 1270 N SUNSET PLAZA DR 90069

Application / Permit
22014-10000-03323
Plan Check / Job No.
B22LA12956
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story addition and interior remodel to (E) 2-Story SFD.
Permit Issued
Issued on 10/13/2022
Issuing Office
Current Status
Issued on 10/13/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/4/2022 APPLICANT
Assigned to Plan Check Engineer 7/15/2022 JOE VO
Corrections Issued 7/17/2022 JOE VO
Quality Review Completed 7/18/2022 GARO TELMI
Plan Check Approved 10/13/2022 JOE VO
Issued 10/13/2022 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/10/2022 TREVOR QUAN
BHO/Hillside ordinance Cleared 8/10/2022 TREVOR QUAN
BHO/Hillside ordinance Cleared 8/10/2022 TREVOR QUAN
Roof/Waste drainage to street Cleared 8/10/2022 TREVOR QUAN
Hydrant and Access approval Cleared 9/16/2022 KURT CORRAL
BHO/Hillside ordinance Cleared 9/19/2022 TREVOR QUAN
BHO/Hillside ordinance Cleared 9/19/2022 TREVOR QUAN
Sewer availability Cleared 9/19/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 9/21/2022 TREVOR QUAN
Grading Pre-Inspection Cleared 10/13/2022 JOE VO

Contact Information

Architect Hefner,, Charles David; Lic. No.: NA23963       ,
Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/14/2022 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 11/1/2022 Partial Approval RAUL BARAJAS
PLUMBING-Rough 11/1/2022 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 11/30/2022 Conditional Approval RAUL BARAJAS
BUILDING-Rough-Frame 12/22/2022 Corrections Issued STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 12/22/2022 Conditional Approval STUART CHAPMAN
Green Building Rough 12/22/2022 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 12/22/2022 Approved STUART CHAPMAN
Shower Pan 1/24/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 2/1/2023 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 2/7/2023 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 2/7/2023 Approved STUART CHAPMAN
Green Building Rough 2/7/2023 Approved STUART CHAPMAN
HVAC-Rough 2/7/2023 Approved STUART CHAPMAN
Insulation 2/13/2023 Approved STUART CHAPMAN
Drywall Nailing 2/23/2023 Approved RAUL BARAJAS
Interior/Exterior Lathing 2/23/2023 Approved RAUL BARAJAS
Green Building Final 6/7/2024 Approved RAUL BARAJAS
Special/Order Compliance 6/7/2024 Corrections Issued RAUL BARAJAS
BUILDING-Rough-Frame 7/25/2024 Not Ready for Inspection RAUL BARAJAS
Final 7/25/2024 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 7/25/2024 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 7/25/2024 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 7/25/2024 Not Ready for Inspection RAUL BARAJAS