1270 N SUNSET PLAZA DR 90069
Certificate Information: 1270 N SUNSET PLAZA DR 90069
- Application / Permit
- 22014-10000-03323
- Plan Check / Job No.
- B22LA12956
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition and interior remodel to (E) 2-Story SFD.
- Permit Issued
- Issued on 10/13/2022
- Issuing Office
- Current Status
- Issued on 10/13/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2022 | JOE VO |
| Corrections Issued | 7/17/2022 | JOE VO |
| Quality Review Completed | 7/18/2022 | GARO TELMI |
| Plan Check Approved | 10/13/2022 | JOE VO |
| Issued | 10/13/2022 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/10/2022 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 8/10/2022 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 8/10/2022 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 8/10/2022 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 9/16/2022 | KURT CORRAL |
| BHO/Hillside ordinance | Cleared | 9/19/2022 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 9/19/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 9/19/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2022 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 10/13/2022 | JOE VO |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: NA23963 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/14/2022 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/1/2022 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 11/1/2022 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/30/2022 | Conditional Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 12/22/2022 | Corrections Issued | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2022 | Conditional Approval | STUART CHAPMAN |
| Green Building Rough | 12/22/2022 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 12/22/2022 | Approved | STUART CHAPMAN |
| Shower Pan | 1/24/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 2/1/2023 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 2/7/2023 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Rough | 2/7/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 2/7/2023 | Approved | STUART CHAPMAN |
| HVAC-Rough | 2/7/2023 | Approved | STUART CHAPMAN |
| Insulation | 2/13/2023 | Approved | STUART CHAPMAN |
| Drywall Nailing | 2/23/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 2/23/2023 | Approved | RAUL BARAJAS |
| Green Building Final | 6/7/2024 | Approved | RAUL BARAJAS |
| Special/Order Compliance | 6/7/2024 | Corrections Issued | RAUL BARAJAS |
| BUILDING-Rough-Frame | 7/25/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 7/25/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 7/25/2024 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 7/25/2024 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 7/25/2024 | Not Ready for Inspection | RAUL BARAJAS |