525 N BELLAGIO TER 90049

Certificate Information: 525 N BELLAGIO TER 90049

Application / Permit
22014-10000-03313
Plan Check / Job No.
B22LA12950
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan REMODEL AND ADDITION TO (E) SFD
Permit Issued
Issued on 12/14/2022
Issuing Office
Current Status
CofO Issued on 2/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/4/2022 APPLICANT
Assigned to Plan Check Engineer 7/21/2022 JAD BASMA
Corrections Issued 7/25/2022 JAD BASMA
Quality Review Completed 8/3/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 9/22/2022 JAD BASMA
Applicant returned to address corrections 9/26/2022 JAD BASMA
Applicant returned to address corrections 10/26/2022 JAD BASMA
Plan Check Approved 10/26/2022 JAD BASMA
Issued 12/14/2022 APPLICANT
CofO in Progress 1/8/2025 MICHAEL PELHAM
CofO Issued 2/1/2025 RICHARD STEINBACH
Permit Finaled 2/1/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/1/2022 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 8/23/2022 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 8/23/2022 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 8/23/2022 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 8/23/2022 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 8/23/2022 ANTHONY MAINEZ
Sewer availability Cleared 8/23/2022 ANTHONY MAINEZ
GPI Written Notices Cleared 9/22/2022 JAD BASMA
Grading Pre-Inspection Cleared 9/22/2022 JAD BASMA
Roof/Waste drainage to street Cleared 9/22/2022 ANTHONY MAINEZ
Low Impact Development Cleared 10/18/2022 CHRIS VONG

Contact Information

Contractor Hanover Builders Inc; Lic. No.: 709353-B 141 DUESENBERG DRIVE STE 6      WESTLAKE VILLAGE, CA 91362

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/25/2023 Not Ready for Inspection CARLOS MATAMOROS
Green Building Rough 9/25/2023 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 11/1/2023 Approved CARLOS MATAMOROS
HVAC-Rough 11/1/2023 Approved CARLOS MATAMOROS
PLUMBING-Rough 11/1/2023 Approved CARLOS MATAMOROS
Wood Frame 11/1/2023 Approved CARLOS MATAMOROS
Insulation 11/7/2023 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 12/1/2023 Approved CARLOS MATAMOROS
Drywall Nailing 12/4/2023 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 12/4/2023 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 12/4/2023 Not Ready for Inspection CARLOS MATAMOROS
Drywall Nailing 12/5/2023 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 3/14/2024 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 3/14/2024 Not Ready for Inspection CARLOS MATAMOROS
Green Building Rough 3/14/2024 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 8/12/2024 Approved CARLOS MATAMOROS
Final 8/12/2024 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 8/12/2024 Approved CARLOS MATAMOROS
Green Building Final 8/12/2024 Approved CARLOS MATAMOROS
HVAC-Final 8/12/2024 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 8/12/2024 SGSOV Not Ready CARLOS MATAMOROS
Smoke Detectors 8/12/2024 Not Ready for Inspection CARLOS MATAMOROS
Pre-Inspection 10/4/2024 Approved CARLOS MATAMOROS
Service/Power Release 10/16/2024 Not Ready for Inspection CARLOS MATAMOROS
Service/Power Release 10/18/2024 Not Ready for Inspection CARLOS MATAMOROS
Service/Power Release 10/28/2024 Approved CARLOS MATAMOROS
Final 11/25/2024 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 11/25/2024 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 11/25/2024 Corrections Issued CARLOS MATAMOROS
Final 1/6/2025 OK to Issue CofO CARLOS MATAMOROS
Smoke Detectors 1/6/2025 Approved CARLOS MATAMOROS