843 N MANSFIELD AVE 90038
Certificate Information: 843 N MANSFIELD AVE 90038
- Application / Permit
- 22014-10000-03298
- Plan Check / Job No.
- B22LA12848
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY ADDITION TO AN EXISTING TWO STORY SFD.
- Permit Issued
- Issued on 11/7/2022
- Issuing Office
- Current Status
- CofO Issued on 10/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 7/26/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 8/2/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 8/3/2022 | APPLICANT |
| Applicant returned to address corrections | 10/6/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 11/3/2022 | MAHNAZ NOURHASHEMI |
| Issued | 11/7/2022 | APPLICANT |
| CofO in Progress | 9/30/2023 | JOAQUIN GREENOUGH |
| Permit Finaled | 10/2/2023 | DEROLD HAUFF |
| CofO Issued | 10/2/2023 | DEROLD HAUFF |
| Permit Finaled | 10/2/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Methane Ordinance | Cleared | 10/21/2022 | PEJMAN NOORI |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2022 | JEANIE LAM |
| Sewer availability | Cleared | 10/25/2022 | JEANIE LAM |
| Low Impact Development | Cleared | 11/1/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 11/1/2022 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/28/2022 | Approved | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 12/1/2022 | Off-Hour Fees Due | |
| Grading Pre-Inspection | 12/1/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 12/13/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 12/13/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| METHANE-Barrier | 12/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 12/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 12/15/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 12/15/2022 | Partial Approval | JOAQUIN GREENOUGH |
| METHANE-Barrier | 12/15/2022 | Approved | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 12/15/2022 | Approved | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 12/22/2022 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 12/22/2022 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 12/29/2022 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 12/29/2022 | Approved | JOSEPH MCGARRY |
| Deputy Steel/Welding | 1/4/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Structural Steel Frame | 1/27/2023 | Partial Approval | STUART CHAPMAN |
| Wood Frame | 1/27/2023 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 2/8/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Rough | 2/8/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Wood Frame | 2/8/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 2/16/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 2/16/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 2/16/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Rough | 2/16/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/2/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 3/2/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Rough | 3/2/2023 | Approved | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 5/12/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2023 | Partial Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 5/16/2023 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 5/19/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 5/19/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Special/Order Compliance | 5/23/2023 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 5/30/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 5/30/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 6/5/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Rough | 6/5/2023 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 6/7/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 6/7/2023 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 6/7/2023 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 6/9/2023 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 6/9/2023 | Approved | JOAQUIN GREENOUGH |
| Insulation | 6/9/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Insulation | 6/9/2023 | Off-Hour Fees Due | |
| Wood Frame | 6/9/2023 | Off-Hour Fees Due | |
| Drywall Nailing | 6/20/2023 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 6/20/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 9/15/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 9/15/2023 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 9/15/2023 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 9/15/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 9/21/2023 | Partial Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 9/21/2023 | SGSOV Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 9/21/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 9/30/2023 | OK to Issue CofO | JOAQUIN GREENOUGH |