629 1/2 W 98TH ST 90044
Certificate Information: 629 1/2 W 98TH ST 90044
- Application / Permit
- 22014-10000-03281
- Plan Check / Job No.
- B22LA12772
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED MAJOR REMODEL AND ADDITION TO REAR UNIT.
- Permit Issued
- Issued on 10/19/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 7/6/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 7/13/2022 | APPLICANT |
| Plan Check Approved | 9/7/2022 | JOSEPH RAFOLS |
| Issued | 10/19/2022 | APPLICANT |
| CofO in Progress | 10/25/2023 | ANSON MAGLASANG |
| Permit Finaled | 10/25/2023 | ANSON MAGLASANG |
| CofO Issued | 10/25/2023 | ANSON MAGLASANG |
| Permit Finaled | 10/25/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/16/2022 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2022 | ELAINE LEI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/4/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 4/6/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 6/2/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2023 | Corrections Issued | JAMES CHAVEZ |
| Green Building Rough | 6/2/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 6/13/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 6/13/2023 | Corrections Issued | JAMES CHAVEZ |
| HVAC-Rough | 6/13/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Masonry Wall/Backfill | 6/13/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 6/13/2023 | Approved | JAMES CHAVEZ |
| Shower Pan | 6/13/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 6/15/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 6/15/2023 | Approved | JAMES CHAVEZ |
| Green Building Final | 6/15/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Green Building Rough | 6/15/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| HVAC-Rough | 6/15/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 6/15/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 6/20/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Green Building Rough | 6/20/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 6/20/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Insulation | 6/22/2023 | Corrections Issued | JAMES CHAVEZ |
| Insulation | 6/26/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 6/30/2023 | No Access for Inspection | JAMES CHAVEZ |
| Interior/Exterior Lathing | 6/30/2023 | No Access for Inspection | JAMES CHAVEZ |
| Drywall Nailing | 7/5/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 7/5/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 8/11/2023 | Approved | JOHN KLARIN |
| Final | 8/11/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 8/11/2023 | Approved | JOHN KLARIN |
| Green Building Final | 8/11/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 8/11/2023 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 8/11/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 8/25/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 10/2/2023 | Corrections Issued | JOHN KLARIN |
| Final | 10/17/2023 | Corrections Issued | JOHN KLARIN |
| Final | 10/23/2023 | OK to Issue CofO | JAMES CHAVEZ |