3079 S MCCONNELL DR 90064
Certificate Information: 3079 S MCCONNELL DR 90064
- Application / Permit
- 22014-10000-03254
- Plan Check / Job No.
- B22LA12648
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND 2-STORY ADDITION TO 1-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 4/17/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | SINA KHOSRAVI |
| Corrections Issued | 7/19/2022 | SINA KHOSRAVI |
| Quality Review Completed | 7/27/2022 | CHARLES CHANG |
| Building Plans Picked Up | 7/29/2022 | APPLICANT |
| Applicant returned to address corrections | 11/14/2022 | SINA KHOSRAVI |
| Plan Check Approved | 2/28/2023 | SINA KHOSRAVI |
| Issued | 4/17/2023 | APPLICANT |
| Permit Finaled | 12/24/2024 | RICHARD STEINBACH |
| CofO Issued | 12/24/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/24/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2022 | WALLIE JONG |
| Sewer availability | Cleared | 8/29/2022 | WALLIE JONG |
| GPI Written Notices | Cleared | 11/14/2022 | SINA KHOSRAVI |
| Grading Pre-Inspection | Cleared | 11/14/2022 | SINA KHOSRAVI |
| Low Impact Development | Cleared | 2/21/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 2/23/2023 | WALLIE JONG |
Contact Information
| Contractor | K & A Construction Development Inc; Lic. No.: 971117-B | 1631 BRYCEDALE AVENUE DUARTE, CA 91010 |
| Engineer | Cai,, Luo; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/7/2023 | Corrections Issued | CLAYTON GRAHAM |
| Special/Order Compliance | 8/8/2023 | Corrections Issued | CLAYTON GRAHAM |
| Piling/Pier/Caisson | 8/14/2023 | Partial Approval | DAVID FEILER |
| Underground Mechanical | 8/14/2023 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 8/17/2023 | Approved | CLAYTON GRAHAM |
| Deputy Reinf. Concrete | 8/21/2023 | Conditional Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2023 | Partial Approval | CLAYTON GRAHAM |
| Underground Mechanical | 9/14/2023 | Partial Approval | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 1/5/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 1/11/2024 | Partial Inspection | JESUS PINEDA |
| HVAC-Rough | 1/19/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 1/19/2024 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 2/1/2024 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/13/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 2/13/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Rough | 2/13/2024 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 2/21/2024 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/28/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 2/28/2024 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2024 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 2/28/2024 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 2/28/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 2/28/2024 | Approved | CARLOS MATAMOROS |
| Insulation | 3/8/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 3/14/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/28/2024 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 3/28/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 10/22/2024 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 10/22/2024 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 10/22/2024 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 10/22/2024 | Corrections Issued | ASHLEY THOMPSON |
| Final | 11/6/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Smoke Detectors | 11/6/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Final | 12/19/2024 | Conditional Approval | REGINA MENDEZ |
| Smoke Detectors | 12/19/2024 | Approved | REGINA MENDEZ |