1518 N CRESCENT HEIGHTS BLVD 90046

Certificate Information: 1518 N CRESCENT HEIGHTS BLVD 90046

Application / Permit
22014-10000-03253
Plan Check / Job No.
B22LA09868
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN ***PROPOSED ADDITION TO AND CONVERSION OF GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d) ***"COMPLY WITH DEPARTMENT ORDER effective date 10/22/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 11/30/2022
Issuing Office
Current Status
CofO Issued on 8/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 SINA KHOSRAVI
Corrections Issued 6/29/2022 SINA KHOSRAVI
Quality Review Completed 7/1/2022 CHARLES CHANG
Applicant returned to address corrections 8/31/2022 SINA KHOSRAVI
Plan Check Approved 11/22/2022 SINA KHOSRAVI
Issued 11/30/2022 APPLICANT
CofO in Progress 5/3/2024 PTOLEMY HILL
Permit Finaled 8/29/2025 DANIEL SANCHEZ
CofO Issued 8/29/2025 DANIEL SANCHEZ
Permit Finaled 8/29/2025 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 7/7/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 7/7/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/11/2022 JEANIE LAM
Sewer availability Cleared 7/11/2022 JEANIE LAM

Contact Information

Contractor United Excavation Group Inc; Lic. No.: 906175-B 6520 PLATT AVENUE #502      WEST HILLS, CA 91307

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/5/2023 Approved PATRICK LIEBREGT
Footing/Foundation/Slab 7/25/2023 Corrections Issued ROBERT MINASSIANS
PLUMBING-Rough 7/25/2023 Partial Approval ROBERT MINASSIANS
Underground Mechanical 7/25/2023 Approved ROBERT MINASSIANS
Footing/Foundation/Slab 7/31/2023 Approved JOEL ORDAZ
Underground Mechanical 7/31/2023 Approved JOEL ORDAZ
ELECTRICAL-Rough 10/6/2023 Corrections Issued JOEL ORDAZ
PLUMBING-Rough 10/6/2023 Approved JOEL ORDAZ
Wood Frame 10/6/2023 Corrections Issued JOEL ORDAZ
ELECTRICAL-Rough 10/11/2023 Approved JOEL ORDAZ
Insulation 10/11/2023 Approved JOEL ORDAZ
PLUMBING-Rough 10/11/2023 Approved JOEL ORDAZ
Floor/Roof Diaphrgm/Shear Wall 10/19/2023 Corrections Issued JOEL ORDAZ
Wood Frame 10/19/2023 Corrections Issued JOEL ORDAZ
Floor/Roof Diaphrgm/Shear Wall 10/27/2023 Approved ARAM AVAKIAN
Wood Frame 10/27/2023 Approved ARAM AVAKIAN
Drywall Nailing 11/13/2023 Approved ARAM AVAKIAN
Interior/Exterior Lathing 11/13/2023 Approved ARAM AVAKIAN
Service/Power Release 12/14/2023 Not Ready for Inspection JOEL ORDAZ
Service/Power Release 12/18/2023 Not Ready for Inspection JOEL ORDAZ
Service/Power Release 12/21/2023 Not Ready for Inspection ARAM AVAKIAN
BUILDING-Rough-Frame 1/29/2024 Approved JOEL ORDAZ
Final 1/29/2024 Corrections Issued JOEL ORDAZ
Green Building Final 1/29/2024 Approved JOEL ORDAZ
Green Building Rough 1/29/2024 Approved JOEL ORDAZ
SGSOV-Seismic Gas S/O Valve 1/29/2024 SGSOV Not Ready JOEL ORDAZ
Smoke Detectors 1/29/2024 Approved JOEL ORDAZ
ELECTRICAL-Final 3/8/2024 Not Ready for Inspection JOEL ORDAZ
Final 3/8/2024 Not Ready for Inspection JOEL ORDAZ
HVAC-Final 3/8/2024 Not Ready for Inspection JOEL ORDAZ
PLUMBING-Final 3/8/2024 Not Ready for Inspection JOEL ORDAZ
SGSOV-Seismic Gas S/O Valve 3/8/2024 SGSOV Not Ready JOEL ORDAZ
Service/Power Release 3/8/2024 Not Required JOEL ORDAZ
ELECTRICAL-Final 4/18/2024 Not Ready for Inspection PTOLEMY HILL
Final 4/18/2024 Not Ready for Inspection PTOLEMY HILL
HVAC-Final 4/18/2024 Corrections Issued PTOLEMY HILL
PLUMBING-Final 4/18/2024 Approved PTOLEMY HILL
SGSOV-Seismic Gas S/O Valve 4/18/2024 SGSOV Approved PTOLEMY HILL
ELECTRICAL-Final 4/23/2024 Approved PTOLEMY HILL
Final 4/23/2024 Conditional Approval PTOLEMY HILL
HVAC-Final 4/23/2024 Approved PTOLEMY HILL
Final 5/3/2024 OK to Issue CofO PTOLEMY HILL