1518 N CRESCENT HEIGHTS BLVD 90046
Certificate Information: 1518 N CRESCENT HEIGHTS BLVD 90046
- Application / Permit
- 22014-10000-03253
- Plan Check / Job No.
- B22LA09868
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN ***PROPOSED ADDITION TO AND CONVERSION OF GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d) ***"COMPLY WITH DEPARTMENT ORDER effective date 10/22/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 11/30/2022
- Issuing Office
- Current Status
- CofO Issued on 8/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2022 | SINA KHOSRAVI |
| Corrections Issued | 6/29/2022 | SINA KHOSRAVI |
| Quality Review Completed | 7/1/2022 | CHARLES CHANG |
| Applicant returned to address corrections | 8/31/2022 | SINA KHOSRAVI |
| Plan Check Approved | 11/22/2022 | SINA KHOSRAVI |
| Issued | 11/30/2022 | APPLICANT |
| CofO in Progress | 5/3/2024 | PTOLEMY HILL |
| Permit Finaled | 8/29/2025 | DANIEL SANCHEZ |
| CofO Issued | 8/29/2025 | DANIEL SANCHEZ |
| Permit Finaled | 8/29/2025 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 7/7/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 7/7/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/11/2022 | JEANIE LAM |
| Sewer availability | Cleared | 7/11/2022 | JEANIE LAM |
Contact Information
| Contractor | United Excavation Group Inc; Lic. No.: 906175-B | 6520 PLATT AVENUE #502 WEST HILLS, CA 91307 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/5/2023 | Approved | PATRICK LIEBREGT |
| Footing/Foundation/Slab | 7/25/2023 | Corrections Issued | ROBERT MINASSIANS |
| PLUMBING-Rough | 7/25/2023 | Partial Approval | ROBERT MINASSIANS |
| Underground Mechanical | 7/25/2023 | Approved | ROBERT MINASSIANS |
| Footing/Foundation/Slab | 7/31/2023 | Approved | JOEL ORDAZ |
| Underground Mechanical | 7/31/2023 | Approved | JOEL ORDAZ |
| ELECTRICAL-Rough | 10/6/2023 | Corrections Issued | JOEL ORDAZ |
| PLUMBING-Rough | 10/6/2023 | Approved | JOEL ORDAZ |
| Wood Frame | 10/6/2023 | Corrections Issued | JOEL ORDAZ |
| ELECTRICAL-Rough | 10/11/2023 | Approved | JOEL ORDAZ |
| Insulation | 10/11/2023 | Approved | JOEL ORDAZ |
| PLUMBING-Rough | 10/11/2023 | Approved | JOEL ORDAZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2023 | Corrections Issued | JOEL ORDAZ |
| Wood Frame | 10/19/2023 | Corrections Issued | JOEL ORDAZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2023 | Approved | ARAM AVAKIAN |
| Wood Frame | 10/27/2023 | Approved | ARAM AVAKIAN |
| Drywall Nailing | 11/13/2023 | Approved | ARAM AVAKIAN |
| Interior/Exterior Lathing | 11/13/2023 | Approved | ARAM AVAKIAN |
| Service/Power Release | 12/14/2023 | Not Ready for Inspection | JOEL ORDAZ |
| Service/Power Release | 12/18/2023 | Not Ready for Inspection | JOEL ORDAZ |
| Service/Power Release | 12/21/2023 | Not Ready for Inspection | ARAM AVAKIAN |
| BUILDING-Rough-Frame | 1/29/2024 | Approved | JOEL ORDAZ |
| Final | 1/29/2024 | Corrections Issued | JOEL ORDAZ |
| Green Building Final | 1/29/2024 | Approved | JOEL ORDAZ |
| Green Building Rough | 1/29/2024 | Approved | JOEL ORDAZ |
| SGSOV-Seismic Gas S/O Valve | 1/29/2024 | SGSOV Not Ready | JOEL ORDAZ |
| Smoke Detectors | 1/29/2024 | Approved | JOEL ORDAZ |
| ELECTRICAL-Final | 3/8/2024 | Not Ready for Inspection | JOEL ORDAZ |
| Final | 3/8/2024 | Not Ready for Inspection | JOEL ORDAZ |
| HVAC-Final | 3/8/2024 | Not Ready for Inspection | JOEL ORDAZ |
| PLUMBING-Final | 3/8/2024 | Not Ready for Inspection | JOEL ORDAZ |
| SGSOV-Seismic Gas S/O Valve | 3/8/2024 | SGSOV Not Ready | JOEL ORDAZ |
| Service/Power Release | 3/8/2024 | Not Required | JOEL ORDAZ |
| ELECTRICAL-Final | 4/18/2024 | Not Ready for Inspection | PTOLEMY HILL |
| Final | 4/18/2024 | Not Ready for Inspection | PTOLEMY HILL |
| HVAC-Final | 4/18/2024 | Corrections Issued | PTOLEMY HILL |
| PLUMBING-Final | 4/18/2024 | Approved | PTOLEMY HILL |
| SGSOV-Seismic Gas S/O Valve | 4/18/2024 | SGSOV Approved | PTOLEMY HILL |
| ELECTRICAL-Final | 4/23/2024 | Approved | PTOLEMY HILL |
| Final | 4/23/2024 | Conditional Approval | PTOLEMY HILL |
| HVAC-Final | 4/23/2024 | Approved | PTOLEMY HILL |
| Final | 5/3/2024 | OK to Issue CofO | PTOLEMY HILL |