6472 W 80TH ST 90045
Certificate Information: 6472 W 80TH ST 90045
- Application / Permit
- 22014-10000-03250
- Plan Check / Job No.
- B22LA12581
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND 2ND STORY ADDITION TO AN EXISTING SFR
- Permit Issued
- Issued on 11/9/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 7/22/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 7/29/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 8/10/2022 | APPLICANT |
| Plan Check Approved | 11/1/2022 | MAHNAZ NOURHASHEMI |
| Issued | 11/9/2022 | APPLICANT |
| CofO in Progress | 5/10/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 5/10/2024 | DANIEL ORRANTE |
| CofO Issued | 5/10/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/10/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 8/20/2022 | STEVEN JIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2022 | JENSON LEE |
| Sewer availability | Cleared | 9/1/2022 | JENSON LEE |
| Trees in Parkway | Cleared | 9/16/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 10/6/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 10/7/2022 | JENSON LEE |
Contact Information
| Contractor | Southland Building & Remodel Company; Lic. No.: 894311-B | 1324 WEST ROSECRANS AVENUE COMPTON, CA 90222 |
| Engineer | Namdar,, Mansour Tom; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/28/2023 | Conditional Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 5/12/2023 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 5/12/2023 | Partial Approval | HERBERT GIRON |
| METHANE-Barrier | 5/12/2023 | Approved | HERBERT GIRON |
| METHANE-Subgrade | 5/12/2023 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 6/28/2023 | Approved | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2023 | Approved | HERBERT GIRON |
| HVAC-Rough | 10/4/2023 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 10/4/2023 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 10/12/2023 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 10/12/2023 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 10/26/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Green Building Rough | 10/26/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 10/26/2023 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 10/26/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 10/31/2023 | Approved | RICHARD STEINBACH |
| Drywall Nailing | 11/7/2023 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 12/8/2023 | Corrections Issued | JESUS PINEDA |
| Shower Pan | 12/8/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 12/12/2023 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 4/18/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Gas Test | 4/18/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 4/18/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Final | 4/18/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 4/29/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 4/29/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 4/29/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 5/6/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 5/6/2024 | Approved | TEMISTOCLES CAAL |
| Final | 5/6/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| Green Building Final | 5/6/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 5/6/2024 | Approved | TEMISTOCLES CAAL |
| METHANE-Final | 5/6/2024 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 5/6/2024 | SGSOV Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 5/6/2024 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 5/8/2024 | Approved | TEMISTOCLES CAAL |