1072 S QUEEN ANNE PL 90019
Certificate Information: 1072 S QUEEN ANNE PL 90019
- Application / Permit
- 22014-10000-03228
- Plan Check / Job No.
- B22LA12510
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Addition to and conversion of existing garage to ADU. per LAMC 12.22 A.33 R3/U occupancy
- Permit Issued
- Issued on 7/9/2024
- Issuing Office
- Current Status
- Issued on 7/9/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | KELVIN CHUONG |
| Corrections Issued | 9/2/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 9/9/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 3/30/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 5/1/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 5/23/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 7/20/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 8/1/2023 | KELVIN CHUONG |
| Plan Check Approved | 8/8/2023 | KELVIN CHUONG |
| No Progress | 1/16/2024 | KELVIN CHUONG |
| Plan Check Approved | 4/23/2024 | KELVIN CHUONG |
| Issued | 7/9/2024 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/5/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/7/2023 | ERNEST TSE |
| Address approval | Cleared | 2/8/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 2/9/2023 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 2/28/2023 | JEANIE LAM |
Contact Information
| Contractor | Master Construction Group Inc; Lic. No.: 1111191-B | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/18/2024 | Approved | JUSTIN HAWLEY |
| METHANE-Barrier | 10/18/2024 | Approved | JUSTIN HAWLEY |
| METHANE-Subgrade | 10/18/2024 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 11/14/2024 | Partial Approval | JOSE MACIAS |
| Green Building Rough | 11/14/2024 | Not Ready for Inspection | JOSE MACIAS |
| METHANE-Rough | 11/14/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 11/14/2024 | Partial Approval | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2024 | Approved | JOSE MACIAS |
| Sewer | 12/13/2024 | Corrections Issued | JOSE MACIAS |
| Sewer | 12/17/2024 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2025 | Corrections Issued | JUSTIN HAWLEY |
| Drywall Nailing | 2/11/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2025 | Partial Approval | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 3/4/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 3/4/2025 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 3/4/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 3/4/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/4/2025 | Approved | ENRIQUE MIRELES |
| Insulation | 3/27/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 3/27/2025 | Partial Approval | ALEX COLIN |
| Shower Pan | 3/27/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 5/7/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 5/7/2025 | Approved | ALEX COLIN |
| Final | 3/10/2026 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 3/10/2026 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 3/10/2026 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 3/10/2026 | Approved | JUSTIN HAWLEY |
| Final | 6/18/2026 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 6/18/2026 | Approved | JUSTIN HAWLEY |