1072 S QUEEN ANNE PL 90019

Certificate Information: 1072 S QUEEN ANNE PL 90019

Application / Permit
22014-10000-03228
Plan Check / Job No.
B22LA12510
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Addition to and conversion of existing garage to ADU. per LAMC 12.22 A.33 R3/U occupancy
Permit Issued
Issued on 7/9/2024
Issuing Office
Current Status
Issued on 7/9/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/1/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 KELVIN CHUONG
Corrections Issued 9/2/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 9/9/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 3/30/2023 KELVIN CHUONG
Applicant returned to address corrections 5/1/2023 KELVIN CHUONG
Applicant returned to address corrections 5/23/2023 KELVIN CHUONG
Applicant returned to address corrections 7/20/2023 KELVIN CHUONG
Applicant returned to address corrections 8/1/2023 KELVIN CHUONG
Plan Check Approved 8/8/2023 KELVIN CHUONG
No Progress 1/16/2024 KELVIN CHUONG
Plan Check Approved 4/23/2024 KELVIN CHUONG
Issued 7/9/2024 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 11/5/2022 RIDWAN HARDY
Low Impact Development Cleared 2/7/2023 ERNEST TSE
Address approval Cleared 2/8/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 2/9/2023 TREVOR QUAN
Sewer availability Cleared 2/9/2023 TREVOR QUAN
Roof/Waste drainage to street Cleared 2/28/2023 JEANIE LAM

Contact Information

Contractor Master Construction Group Inc; Lic. No.: 1111191-B       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/18/2024 Approved JUSTIN HAWLEY
METHANE-Barrier 10/18/2024 Approved JUSTIN HAWLEY
METHANE-Subgrade 10/18/2024 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 11/14/2024 Partial Approval JOSE MACIAS
Green Building Rough 11/14/2024 Not Ready for Inspection JOSE MACIAS
METHANE-Rough 11/14/2024 Approved JOSE MACIAS
PLUMBING-Rough 11/14/2024 Partial Approval JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Approved JOSE MACIAS
Sewer 12/13/2024 Corrections Issued JOSE MACIAS
Sewer 12/17/2024 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Corrections Issued JUSTIN HAWLEY
Drywall Nailing 2/11/2025 Not Ready for Inspection NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 2/11/2025 Partial Approval NICHOLAS LOPEZ
BUILDING-Rough-Frame 3/4/2025 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 3/4/2025 Approved ENRIQUE MIRELES
Green Building Rough 3/4/2025 Approved ENRIQUE MIRELES
HVAC-Rough 3/4/2025 Approved ENRIQUE MIRELES
PLUMBING-Rough 3/4/2025 Approved ENRIQUE MIRELES
Insulation 3/27/2025 Approved ALEX COLIN
Interior/Exterior Lathing 3/27/2025 Partial Approval ALEX COLIN
Shower Pan 3/27/2025 Approved ALEX COLIN
Drywall Nailing 5/7/2025 Approved ALEX COLIN
Interior/Exterior Lathing 5/7/2025 Approved ALEX COLIN
Final 3/10/2026 Corrections Issued JUSTIN HAWLEY
Green Building Final 3/10/2026 Not Ready for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 3/10/2026 SGSOV Approved JUSTIN HAWLEY
Smoke Detectors 3/10/2026 Approved JUSTIN HAWLEY
Final 6/18/2026 Corrections Issued JUSTIN HAWLEY
Green Building Final 6/18/2026 Approved JUSTIN HAWLEY