7702 N WINNETKA AVE 91306

Certificate Information: 7702 N WINNETKA AVE 91306

Application / Permit
22014-10000-03224
Plan Check / Job No.
B22LA12506
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE INTO ADU AND AN ADDITION (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 8/17/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2022 APPLICANT
Assigned to Plan Check Engineer 6/28/2022 AUNG SOE
Corrections Issued 7/1/2022 AUNG SOE
Building Plans Picked Up 7/14/2022 APPLICANT
Plan Check Approved 8/9/2022 SAMUEL GONZALEZ
Issued 8/17/2022 APPLICANT
CofO in Progress 11/16/2022 STEVEN BACK
Permit Finaled 11/18/2022 JOHN JANSON
CofO Issued 11/18/2022 JOHN JANSON
Permit Finaled 11/18/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/27/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/27/2022 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 7/27/2022 LEE GUILBEAUX
Sewer availability Cleared 7/27/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/24/2022 Partial Approval STEVEN BACK
Deputy Drilled-In Anchors 8/26/2022 Conditional Approval JOHN JANSON
Footing/Foundation/Slab 9/2/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 9/21/2022 Approved STEVEN BACK
HVAC-Rough 9/21/2022 Approved STEVEN BACK
PLUMBING-Rough 9/21/2022 Approved STEVEN BACK
Pre-Inspection 9/21/2022 Partial Inspection STEVEN BACK
BUILDING-Rough-Frame 9/28/2022 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/28/2022 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 10/3/2022 Approved DAVID SCANTLIN
Green Building Rough 10/3/2022 Approved DAVID SCANTLIN
Interior/Exterior Lathing 10/3/2022 Partial Approval DAVID SCANTLIN
Shower Pan 10/3/2022 Approved DAVID SCANTLIN
Drywall Nailing 10/11/2022 Approved STEVEN BACK
Insulation 10/11/2022 Approved STEVEN BACK
Interior/Exterior Lathing 10/11/2022 Approved STEVEN BACK
Sewer 10/11/2022 Approved STEVEN BACK
Underground Mechanical 10/11/2022 Approved STEVEN BACK
Underground Mechanical 10/28/2022 Partial Approval STEVEN BACK
ELECTRICAL-Final 11/16/2022 Approved STEVEN BACK
Final 11/16/2022 OK to Issue CofO STEVEN BACK
Gas Test 11/16/2022 Approved STEVEN BACK
Green Building Final 11/16/2022 Approved STEVEN BACK
HVAC-Final 11/16/2022 Approved STEVEN BACK
PLUMBING-Final 11/16/2022 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 11/16/2022 SGSOV Approved STEVEN BACK
Service/Power Release 11/16/2022 Approved STEVEN BACK
Smoke Detectors 11/16/2022 Approved STEVEN BACK