7200 S ARIZONA AVE 90045

Certificate Information: 7200 S ARIZONA AVE 90045

Application / Permit
22014-10000-03213
Plan Check / Job No.
B22LA12476
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan Interior remodel of existing single story SFD. Work includes enclosing the existing carport and convert to two-car garage and converting portion of existing carport to interior residential area. Work also includes single story addition.
Permit Issued
Issued on 8/24/2022
Issuing Office
Current Status
CofO Issued on 8/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2022 APPLICANT
Assigned to Plan Check Engineer 7/1/2022 FARSHAD ALIMOHAMADI
Corrections Issued 7/4/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 7/25/2022 FARSHAD ALIMOHAMADI
Issued 8/24/2022 APPLICANT
CofO in Progress 8/9/2023 HERBERT GIRON
Permit Finaled 8/15/2023 DANIEL ORRANTE
CofO Issued 8/15/2023 DANIEL ORRANTE
Permit Finaled 8/15/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/13/2022 DINAH GARIN
Roof/Waste drainage to street Cleared 7/13/2022 DINAH GARIN
Sewer availability Cleared 7/13/2022 DINAH GARIN
Specific Plan Cleared 7/14/2022 VALERIA CEJA
Grading Pre-Inspection Cleared 7/25/2022 FARSHAD ALIMOHAMADI

Contact Information

Architect Hamilton,, John Patrick; Lic. No.: NA28865       ,
Contractor Chadwick & Doggett General Contracting Inc; Lic. No.: 756093-B       ,
Engineer Le,, Thang Huu; Lic. No.: NA4978       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/26/2022 Partial Approval HERBERT GIRON
PLUMBING-Rough 10/3/2022 Corrections Issued HERBERT GIRON
Deputy Drilled-In Anchors 10/4/2022 Conditional Approval CLAYTON GRAHAM
PLUMBING-Rough 10/5/2022 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 10/6/2022 Partial Approval HERBERT GIRON
METHANE-Barrier 10/6/2022 Approved HERBERT GIRON
METHANE-Subgrade 10/6/2022 Approved HERBERT GIRON
Deputy Wood Construction 10/28/2022 Approved HERBERT GIRON
PLUMBING-Rough 10/28/2022 Partial Approval HERBERT GIRON
Deputy Wood Construction 10/31/2022 Conditional Approval HERBERT GIRON
PLUMBING-Rough 12/13/2022 Corrections Issued HERBERT GIRON
Wood Frame 12/13/2022 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 12/21/2022 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 12/29/2022 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 1/11/2023 Conditional Approval HERBERT GIRON
METHANE-Rough 1/11/2023 Approved HERBERT GIRON
PLUMBING-Rough 1/11/2023 Conditional Approval HERBERT GIRON
Shower Pan 1/13/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 1/18/2023 Partial Approval HERBERT GIRON
HVAC-Rough 1/20/2023 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 1/20/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 1/27/2023 Corrections Issued HERBERT GIRON
Green Building Rough 1/27/2023 Approved HERBERT GIRON
HVAC-Rough 1/27/2023 Approved HERBERT GIRON
Insulation 1/27/2023 Approved HERBERT GIRON
Drywall Nailing 2/7/2023 Approved HERBERT GIRON
Gas Test 5/23/2023 Approved HERBERT GIRON
PLUMBING-Rough 5/23/2023 Approved HERBERT GIRON
HVAC-Final 7/17/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 7/17/2023 Approved HERBERT GIRON
ELECTRICAL-Final 7/18/2023 Corrections Issued DAVID FEILER
Smoke Detectors 7/18/2023 Approved DAVID FEILER
ELECTRICAL-Final 8/3/2023 Approved BOBBY KEY
HVAC-Final 8/3/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 8/7/2023 Not Ready for Inspection HERBERT GIRON
Final 8/7/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 8/7/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 8/7/2023 SGSOV Approved HERBERT GIRON
BUILDING-Rough-Frame 8/9/2023 Approved HERBERT GIRON
Final 8/9/2023 OK to Issue CofO HERBERT GIRON