7803 N WHITE OAK AVE 91335

Certificate Information: 7803 N WHITE OAK AVE 91335

Application / Permit
22014-10000-03208
Plan Check / Job No.
B22LA12463
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. CONVERSION OF (E) GARAGE & ADDITION FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)&(d)
Permit Issued
Issued on 10/25/2022
Issuing Office
Current Status
CofO Issued on 10/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/5/2022 APPLICANT
Assigned to Plan Check Engineer 7/28/2022 LAMAR DAVIS
Corrections Issued 8/4/2022 LAMAR DAVIS
Quality Review Completed 8/10/2022 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 10/21/2022 LAMAR DAVIS
Issued 10/25/2022 APPLICANT
CofO in Progress 8/18/2023 JEFFREY BULL
CofO Issued 10/10/2023 JOHN JANSON
Permit Finaled 10/10/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/11/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 9/21/2022 COLIN LOREDO
Sewer availability Cleared 9/21/2022 COLIN LOREDO
Low Impact Development Cleared 10/14/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 10/17/2022 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/2/2022 Approved JEFFREY BULL
Deputy Drilled-In Anchors 11/30/2022 Partial Approval SEAN WIRCH
Excavation/Setback/Form/Re-Bar 12/8/2022 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 12/30/2022 Not Ready for Inspection ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 1/4/2023 Partial Approval JEFFREY BULL
BUILDING-Rough-Frame 1/20/2023 Not Ready for Inspection JEFFREY BULL
Green Building Rough 1/20/2023 Not Ready for Inspection JEFFREY BULL
ELECTRICAL-Rough 2/28/2023 Approved JUSTIN HAWLEY
HVAC-Rough 2/28/2023 Approved JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 2/28/2023 Approved JUSTIN HAWLEY
Special/Order Compliance 2/28/2023 Corrections Issued SEAN HAUPT
Underground Mechanical 2/28/2023 Approved JUSTIN HAWLEY
Wood Frame 2/28/2023 Not Ready for Inspection JUSTIN HAWLEY
BUILDING-Rough-Frame 3/7/2023 Approved JEFFREY BULL
ELECTRICAL-Rough 3/7/2023 Approved JEFFREY BULL
Green Building Rough 3/7/2023 Approved JEFFREY BULL
HVAC-Rough 3/7/2023 Approved JEFFREY BULL
PLUMBING-Rough 3/7/2023 Approved JEFFREY BULL
Insulation 4/7/2023 Approved JEFFREY BULL
Drywall Nailing 4/12/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 4/12/2023 Partial Approval JEFFREY BULL
Final 7/11/2023 Corrections Issued JUSTIN HAWLEY
HVAC-Final 7/11/2023 Corrections Issued JUSTIN HAWLEY
PLUMBING-Final 7/11/2023 Corrections Issued JUSTIN HAWLEY
Service/Power Release 7/11/2023 Corrections Issued JUSTIN HAWLEY
Smoke Detectors 7/11/2023 Not Ready for Inspection JUSTIN HAWLEY
ELECTRICAL-Final 8/17/2023 Approved JEFFREY BULL
Final 8/17/2023 OK to Issue CofO JEFFREY BULL
Footing/Foundation/Slab 8/17/2023 Approved JEFFREY BULL
Green Building Final 8/17/2023 Approved JEFFREY BULL
HVAC-Final 8/17/2023 Approved JEFFREY BULL
PLUMBING-Final 8/17/2023 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 8/17/2023 SGSOV Approved JEFFREY BULL
Smoke Detectors 8/17/2023 Approved JEFFREY BULL