2046 W 92ND ST 90047
Certificate Information: 2046 W 92ND ST 90047
- Application / Permit
- 22014-10000-03198
- Plan Check / Job No.
- B22LA12457
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EXISTING ONE STORY SINGLE FAMILY DEWELLING PER ENGINEER DESIGN
- Permit Issued
- Issued on 8/5/2022
- Issuing Office
- Metro
- Current Status
- Issued on 8/5/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2022 | AUNG SOE |
| Corrections Issued | 7/1/2022 | AUNG SOE |
| Building Plans Picked Up | 7/18/2022 | APPLICANT |
| Applicant returned to address corrections | 7/29/2022 | MINA HABILI |
| Applicant returned to address corrections | 8/5/2022 | DANIEL SANJUAN |
| Plan Check Approved | 8/5/2022 | DANIEL SANJUAN |
| Issued | 8/5/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 7/18/2022 | CINDY QI |
| Sewer availability | Cleared | 7/18/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/23/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 4/3/2023 | Partial Approval | STUART CHAPMAN |
| Insulation | 4/10/2023 | Approved | ENRIQUE MIRELES |
| Wood Frame | 4/21/2023 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/13/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 6/13/2023 | Approved | ENRIQUE MIRELES |
| METHANE-Rough | 6/13/2023 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 6/13/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 8/2/2023 | No Access for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/2/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Wood Frame | 8/2/2023 | No Access for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/3/2023 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/17/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/17/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 11/14/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/14/2023 | Corrections Issued | ENRIQUE MIRELES |
| Drywall Nailing | 1/2/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 1/2/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/2/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 1/19/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 1/19/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 1/19/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 2/14/2024 | Approved | JOSE MACIAS |
| Insulation | 2/14/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 2/14/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 2/29/2024 | Approved | JOSE MACIAS |
| Shower Pan | 3/14/2024 | Corrections Issued | MICHAEL LEWIS |
| Sewer | 4/29/2024 | Corrections Issued | JOSE MACIAS |
| Shower Pan | 4/29/2024 | Approved | JOSE MACIAS |
| Shower Pan | 4/30/2024 | Partial Inspection | JOSH MEISTER |
| Interior/Exterior Lathing | 5/8/2024 | Approved | JOSE MACIAS |