- conversion of (e) garage to (n) ADU w/ addition per LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 5/9/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | KELVIN CHUONG |
| Corrections Issued | 8/2/2022 | KELVIN CHUONG |
| Quality Review Completed | 8/5/2022 | KEN GILL |
| Building Plans Picked Up | 8/8/2022 | APPLICANT |
| Applicant returned to address corrections | 8/11/2022 | KELVIN CHUONG |
| Applicant returned to address corrections | 3/7/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 4/13/2023 | KELVIN CHUONG |
| Plan Check Approved | 4/18/2023 | KELVIN CHUONG |
| Issued | 5/9/2023 | APPLICANT |
| CofO in Progress | 7/24/2025 | MATTHEW NELSON |
| Permit Finaled | 8/4/2025 | RUBEN SALAS |
| CofO Issued | 8/4/2025 | RUBEN SALAS |
| Permit Finaled | 8/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/1/2022 | KIRK LINKLATER |
| Address approval | Cleared | 8/2/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/2/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 9/2/2022 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 9/2/2022 | JOHN LIN |
| Specific Plan | Cleared | 9/8/2022 | SARAH HOUNSELL |
| GPI Written Notices | Cleared | 3/7/2023 | KELVIN CHUONG |
| Zoning Information File | Cleared | 4/13/2023 | KELVIN CHUONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/18/2023 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 6/14/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 8/8/2023 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 8/8/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 9/14/2023 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 9/14/2023 | Not Ready for Inspection | WILLIAM WREN |
| Green Building Rough | 9/14/2023 | Not Ready for Inspection | WILLIAM WREN |
| HVAC-Rough | 9/14/2023 | Corrections Issued | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Corrections Issued | WILLIAM WREN |
| HVAC-Rough | 10/24/2023 | Approved | WILLIAM WREN |
| Deputy Wood Construction | 10/26/2023 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 11/27/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 12/6/2023 | Approved | WILLIAM WREN |
| Green Building Rough | 12/6/2023 | Approved | WILLIAM WREN |
| Insulation | 12/19/2023 | Corrections Issued | WILLIAM WREN |
| Shower Pan | 12/19/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 1/11/2024 | Corrections Issued | WILLIAM WREN |
| Drywall Nailing | 1/23/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/30/2024 | Approved | CRAIG DAVIS |
| Interior/Exterior Lathing | 3/27/2024 | Approved | WILLIAM WREN |
| Final | 3/24/2025 | Not Ready for Inspection | WILLIAM WREN |
| Footing/Foundation/Slab | 3/24/2025 | Not Ready for Inspection | WILLIAM WREN |
| Green Building Final | 3/24/2025 | Not Ready for Inspection | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 3/24/2025 | SGSOV Not Ready | WILLIAM WREN |
| Smoke Detectors | 3/24/2025 | Not Ready for Inspection | WILLIAM WREN |
| Final | 5/19/2025 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 5/19/2025 | Approved | WILLIAM WREN |
| Green Building Final | 5/19/2025 | Not Ready for Inspection | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Approved | WILLIAM WREN |
| Smoke Detectors | 5/19/2025 | Approved | WILLIAM WREN |
| Final | 7/3/2025 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 7/3/2025 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 7/10/2025 | No Access for Inspection | MICHEL ABAJAN |
| Final | 7/10/2025 | No Access for Inspection | MICHEL ABAJAN |
| HVAC-Final | 7/10/2025 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 7/10/2025 | No Access for Inspection | MICHEL ABAJAN |
| Final | 7/15/2025 | OK to Issue CofO | MATTHEW NELSON |