8437 S TRUXTON AVE 90045

Certificate Information: 8437 S TRUXTON AVE 90045

Application / Permit
22014-10000-03188
Plan Check / Job No.
B22LA12445
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN. NFPA13D FIRE SPRINKLERS REQUIRED. NEW ADDITION AT REAR OF (E) SINGLE FAMILY DWELLING. INTERIOR/EXTERIOR REMODEL.
Permit Issued
Issued on 8/4/2022
Issuing Office
Current Status
CofO Issued on 2/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2022 APPLICANT
Assigned to Plan Check Engineer 7/5/2022 KEVIN MORALES
Corrections Issued 7/5/2022 KEVIN MORALES
Plan Check Approved 8/2/2022 KEVIN MORALES
Issued 8/4/2022 APPLICANT
CofO in Progress 2/21/2023 BOBBY KEY
Permit Finaled 2/25/2023 DANIEL ORRANTE
CofO Issued 2/25/2023 DANIEL ORRANTE
Permit Finaled 2/25/2023 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 7/20/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/21/2022 DINAH GARIN
Low Impact Development Cleared 7/29/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 8/2/2022 DENNIS BRAGIN

Contact Information

Contractor N A N D C O Llc; Lic. No.: 1044615-B       ,
Contractor Nandco Construction; Lic. No.: 1044615-B       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 9/7/2022 Not Ready for Inspection BOBBY KEY
Excavation/Setback/Form/Re-Bar 9/7/2022 Approved BOBBY KEY
Footing/Foundation/Slab 9/7/2022 Approved BOBBY KEY
Deputy Reinf. Concrete 9/12/2022 Conditional Approval BOBBY KEY
PLUMBING-Rough 9/19/2022 Partial Approval BOBBY KEY
Sewer 9/19/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Partial Approval BOBBY KEY
ELECTRICAL-Rough 10/18/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 10/18/2022 Approved BOBBY KEY
HVAC-Rough 10/18/2022 Approved BOBBY KEY
PLUMBING-Rough 10/18/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 11/2/2022 Approved BOBBY KEY
Final 11/2/2022 Corrections Issued BOBBY KEY
Green Building Rough 11/2/2022 Approved BOBBY KEY
Interior/Exterior Lathing 11/2/2022 Partial Approval BOBBY KEY
Insulation 11/7/2022 Partial Approval BOBBY KEY
Interior/Exterior Lathing 11/7/2022 Approved BOBBY KEY
Shower Pan 11/7/2022 Approved BOBBY KEY
Drywall Nailing 11/14/2022 Approved BOBBY KEY
ELECTRICAL-Final 1/25/2023 Corrections Issued BOBBY KEY
Final 1/25/2023 Corrections Issued BOBBY KEY
Gas Test 1/25/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 1/25/2023 SGSOV Approved BOBBY KEY
Smoke Detectors 1/25/2023 Approved BOBBY KEY
ELECTRICAL-Final 2/1/2023 Approved BOBBY KEY
Final 2/1/2023 Not Ready for Inspection BOBBY KEY
HVAC-Final 2/1/2023 Approved BOBBY KEY
PLUMBING-Final 2/1/2023 Approved BOBBY KEY
Service/Power Release 2/1/2023 Not Ready for Inspection BOBBY KEY
Final 2/21/2023 OK to Issue CofO BOBBY KEY
Service/Power Release 2/21/2023 Approved BOBBY KEY