425 E CULVER BLVD 90293
Certificate Information: 425 E CULVER BLVD 90293
- Application / Permit
- 22014-10000-03176
- Plan Check / Job No.
- B22LA12433
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Eplan. Remodel (E) duplex and remove 2nd story deck.
- Permit Issued
- Issued on 1/9/2023
- Issuing Office
- Current Status
- Permit Finaled on 12/5/2025
Permit Application Status History
| Submitted | 6/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | HELEN NGUYEN |
| Corrections Issued | 8/2/2022 | LAMAR DAVIS |
| Quality Review Completed | 8/9/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 12/9/2022 | HELEN NGUYEN |
| Plan Check Approved | 12/14/2022 | HELEN NGUYEN |
| Issued | 1/9/2023 | APPLICANT |
| Permit Finaled | 12/1/2025 | JESUS PINEDA |
| CofO in Progress | 12/1/2025 | JESUS PINEDA |
| No Progress | 12/5/2025 | DAVID FEILER |
| CofO in Progress | 12/5/2025 | DAVID FEILER |
Permit Application Clearance Information
| "D" conditions | Cleared | 8/25/2022 | RYAN LY |
| "Q" conditions | Cleared | 9/1/2022 | ANACANY HURTADO |
| Coastal Zone | Cleared | 12/6/2022 | RYAN LY |
| Sewer availability | Cleared | 12/7/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2022 | DINAH GARIN |
| Public Works-Highway Ded. | Cleared | 8/13/2025 | CHRISTINE REUSCH |
| Public Works-Open Permits | Cleared | 8/13/2025 | CHRISTINE REUSCH |
| Public Works-Sewers | Cleared | 8/13/2025 | CHRISTINE REUSCH |
Contact Information
| Architect | Wagner,, Warren Wolff; Lic. No.: C19875 | 1337 PALMS BLVD VENICE, CA 90291 |
| Contractor | Owner-Builder | , |
| Engineer | Parker,, Leo Augustine; Lic. No.: S2829 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/17/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 2/17/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Partial Approval | BOBBY KEY |
| Green Building Rough | 3/7/2023 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 3/28/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2023 | Partial Approval | BOBBY KEY |
| Insulation | 5/9/2023 | Partial Approval | BOBBY KEY |
| Pre-Inspection | 5/24/2023 | Partial Inspection | BOBBY KEY |
| Sewer | 6/14/2023 | No Access for Inspection | BOBBY KEY |
| PLUMBING-Rough | 6/15/2023 | Partial Approval | BOBBY KEY |
| Sewer | 6/15/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 9/19/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 9/21/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 9/21/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 9/21/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 9/21/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 10/2/2023 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 10/2/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 10/2/2023 | Approved | BOBBY KEY |
| Green Building Rough | 10/2/2023 | Not Ready for Inspection | BOBBY KEY |
| Shower Pan | 10/2/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 10/10/2023 | Approved | BOBBY KEY |
| Green Building Rough | 10/10/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/10/2023 | Partial Approval | BOBBY KEY |
| Insulation | 10/18/2023 | Approved | KENNETH NAGLE |
| Drywall Nailing | 11/13/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 12/6/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 1/23/2024 | Partial Approval | BOBBY KEY |
| Service/Power Release | 1/23/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 6/18/2024 | Conditional Approval | BOBBY KEY |
| Green Building Final | 6/18/2024 | Not Ready for Inspection | BOBBY KEY |
| Service/Power Release | 6/18/2024 | Approved | BOBBY KEY |
| Final | 7/18/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 7/18/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Final | 7/18/2025 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/18/2025 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 7/18/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 7/30/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 7/30/2025 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 7/30/2025 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 7/30/2025 | Approved | JESUS PINEDA |
| Final | 11/20/2025 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Final | 11/20/2025 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Final | 11/20/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 11/20/2025 | Approved | JESUS PINEDA |
| Final | 12/1/2025 | Permit Finaled | JESUS PINEDA |
| Green Building Final | 12/1/2025 | Approved | JESUS PINEDA |