425 E CULVER BLVD 90293

Certificate Information: 425 E CULVER BLVD 90293

Application / Permit
22014-10000-03176
Plan Check / Job No.
B22LA12433
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Eplan. Remodel (E) duplex and remove 2nd story deck.
Permit Issued
Issued on 1/9/2023
Issuing Office
Current Status
Permit Finaled on 12/5/2025

Permit Application Status History

Submitted 6/28/2022 APPLICANT
Assigned to Plan Check Engineer 7/28/2022 HELEN NGUYEN
Corrections Issued 8/2/2022 LAMAR DAVIS
Quality Review Completed 8/9/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 12/9/2022 HELEN NGUYEN
Plan Check Approved 12/14/2022 HELEN NGUYEN
Issued 1/9/2023 APPLICANT
Permit Finaled 12/1/2025 JESUS PINEDA
CofO in Progress 12/1/2025 JESUS PINEDA
No Progress 12/5/2025 DAVID FEILER
CofO in Progress 12/5/2025 DAVID FEILER

Permit Application Clearance Information

"D" conditions Cleared 8/25/2022 RYAN LY
"Q" conditions Cleared 9/1/2022 ANACANY HURTADO
Coastal Zone Cleared 12/6/2022 RYAN LY
Sewer availability Cleared 12/7/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 12/9/2022 DINAH GARIN
Public Works-Highway Ded. Cleared 8/13/2025 CHRISTINE REUSCH
Public Works-Open Permits Cleared 8/13/2025 CHRISTINE REUSCH
Public Works-Sewers Cleared 8/13/2025 CHRISTINE REUSCH

Contact Information

Architect Wagner,, Warren Wolff; Lic. No.: C19875 1337 PALMS BLVD      VENICE, CA 90291
Contractor Owner-Builder       ,
Engineer Parker,, Leo Augustine; Lic. No.: S2829 1927 PONTIUS AVE      LOS ANGELES, CA 90025

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/17/2023 Partial Approval BOBBY KEY
Footing/Foundation/Slab 2/17/2023 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Partial Approval BOBBY KEY
Green Building Rough 3/7/2023 Not Ready for Inspection BOBBY KEY
Footing/Foundation/Slab 3/28/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/9/2023 Partial Approval BOBBY KEY
Insulation 5/9/2023 Partial Approval BOBBY KEY
Pre-Inspection 5/24/2023 Partial Inspection BOBBY KEY
Sewer 6/14/2023 No Access for Inspection BOBBY KEY
PLUMBING-Rough 6/15/2023 Partial Approval BOBBY KEY
Sewer 6/15/2023 Approved BOBBY KEY
PLUMBING-Rough 9/19/2023 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 9/21/2023 Not Ready for Inspection BOBBY KEY
HVAC-Final 9/21/2023 Corrections Issued BOBBY KEY
HVAC-Rough 9/21/2023 Approved BOBBY KEY
PLUMBING-Rough 9/21/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 9/25/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 10/2/2023 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 10/2/2023 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 10/2/2023 Approved BOBBY KEY
Green Building Rough 10/2/2023 Not Ready for Inspection BOBBY KEY
Shower Pan 10/2/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 10/10/2023 Approved BOBBY KEY
Green Building Rough 10/10/2023 Approved BOBBY KEY
Interior/Exterior Lathing 10/10/2023 Partial Approval BOBBY KEY
Insulation 10/18/2023 Approved KENNETH NAGLE
Drywall Nailing 11/13/2023 Approved BOBBY KEY
Interior/Exterior Lathing 12/6/2023 Approved BOBBY KEY
ELECTRICAL-Final 1/23/2024 Partial Approval BOBBY KEY
Service/Power Release 1/23/2024 Approved BOBBY KEY
ELECTRICAL-Final 6/18/2024 Conditional Approval BOBBY KEY
Green Building Final 6/18/2024 Not Ready for Inspection BOBBY KEY
Service/Power Release 6/18/2024 Approved BOBBY KEY
Final 7/18/2025 Corrections Issued JESUS RODRIGUEZ
Green Building Final 7/18/2025 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Final 7/18/2025 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/18/2025 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 7/18/2025 Corrections Issued JESUS RODRIGUEZ
Final 7/30/2025 Corrections Issued JESUS PINEDA
Green Building Final 7/30/2025 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 7/30/2025 SGSOV Approved JESUS PINEDA
Smoke Detectors 7/30/2025 Approved JESUS PINEDA
Final 11/20/2025 Not Ready for Inspection JESUS PINEDA
Green Building Final 11/20/2025 Not Ready for Inspection JESUS PINEDA
HVAC-Final 11/20/2025 Approved JESUS PINEDA
PLUMBING-Final 11/20/2025 Approved JESUS PINEDA
Final 12/1/2025 Permit Finaled JESUS PINEDA
Green Building Final 12/1/2025 Approved JESUS PINEDA