1578 S ROXBURY DR 90035

Certificate Information: 1578 S ROXBURY DR 90035

Application / Permit
22014-10000-03151
Plan Check / Job No.
B22LA12225
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDTION TO EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
Permit Issued
Issued on 1/17/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2022 APPLICANT
Assigned to Plan Check Engineer 7/7/2022 MAHNAZ NOURHASHEMI
Corrections Issued 7/14/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 7/22/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 7/26/2022 APPLICANT
Applicant returned to address corrections 11/29/2022 MAHNAZ NOURHASHEMI
Plan Check Approved 12/1/2022 MAHNAZ NOURHASHEMI
Issued 1/17/2023 APPLICANT
CofO in Progress 4/2/2025 ARAM AVEDISIAN
Permit Finaled 4/3/2025 RICHARD STEINBACH
CofO Issued 4/3/2025 RICHARD STEINBACH
Permit Finaled 4/3/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 7/27/2022 VALERIA CEJA
ZI Cleared 7/28/2022 MAYELA VILLA
Eng Process Fee Ord 176,300 Cleared 8/15/2022 SAUL GARCIA
Sewer availability Cleared 8/15/2022 SAUL GARCIA
Roof/Waste drainage to street Cleared 9/27/2022 DINAH GARIN
GPI Written Notices Cleared 9/28/2022 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 9/28/2022 MAHNAZ NOURHASHEMI
Hydrant and Access approval Cleared 11/12/2022 GILBERT URREA
Excavation more than 5-ft deep Cleared 11/29/2022 CALOSHA APPROVED
Watercourse Cleared 11/30/2022 HISASHI KOBAYAKAWA
Low Impact Development Cleared 12/1/2022 ROGELIO CORTES

Contact Information

Contractor Drexel Construction Management Llc; Lic. No.: 1014160-B 5168 W PICO BLVD      LOS ANGELES, CA 90019
Engineer Martirossyan,, Armen; Lic. No.: C64223 802 PORTOLA AVE      GLENDALE, CA 91206

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/25/2023 Partial Approval CLAYTON GRAHAM
METHANE-Barrier 4/25/2023 Not Ready for Inspection CLAYTON GRAHAM
METHANE-Subgrade 4/25/2023 Not Ready for Inspection CLAYTON GRAHAM
Footing/Foundation/Slab 5/24/2023 Partial Approval CLAYTON GRAHAM
METHANE-Barrier 5/24/2023 Not Ready for Inspection CLAYTON GRAHAM
METHANE-Subgrade 5/24/2023 Not Ready for Inspection CLAYTON GRAHAM
METHANE-Subgrade 6/13/2023 Partial Approval CLAYTON GRAHAM
Underground Mechanical 6/13/2023 Not Ready for Inspection CLAYTON GRAHAM
Footing/Foundation/Slab 6/26/2023 Corrections Issued CLAYTON GRAHAM
METHANE-Barrier 6/26/2023 Not Ready for Inspection CLAYTON GRAHAM
METHANE-Subgrade 6/26/2023 Partial Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 7/24/2023 Not Ready for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 8/3/2023 Partial Approval CHRISTOPHER WILSON
METHANE-Subgrade 8/30/2023 Approved CLAYTON GRAHAM
PLUMBING-Rough 8/30/2023 Partial Approval CLAYTON GRAHAM
Footing/Foundation/Slab 9/8/2023 Corrections Issued CLAYTON GRAHAM
METHANE-Barrier 9/8/2023 Not Ready for Inspection CLAYTON GRAHAM
Excavation/Setback/Form/Re-Bar 9/12/2023 Approved CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Corrections Issued CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 10/30/2023 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 Partial Approval MEL KHACHATOURIAN
Sewer 1/26/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 1/29/2024 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/8/2024 Partial Approval OGANES TARAKHCHYAN
Shower Pan 2/28/2024 Approved MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 3/22/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/2/2024 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 4/15/2024 Corrections Issued OGANES TARAKHCHYAN
HVAC-Rough 4/15/2024 Corrections Issued OGANES TARAKHCHYAN
HVAC-Rough 4/18/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/8/2024 Partial Inspection OGANES TARAKHCHYAN
METHANE-Rough 5/8/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/29/2024 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Rough 5/29/2024 Not Ready for Inspection ASHLEY THOMPSON
FLOOD-Proofing Certificate 5/29/2024 Approved ASHLEY THOMPSON
Green Building Rough 5/29/2024 Corrections Issued ASHLEY THOMPSON
Interior/Exterior Lathing 5/29/2024 Corrections Issued ASHLEY THOMPSON
BUILDING-Rough-Frame 6/14/2024 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 6/14/2024 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Rough 6/14/2024 Not Ready for Inspection MEL KHACHATOURIAN
Interior/Exterior Lathing 6/14/2024 Not Ready for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 6/14/2024 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 6/18/2024 Approved MEL KHACHATOURIAN
ELECTRICAL-Rough 6/18/2024 Partial Approval MEL KHACHATOURIAN
Green Building Rough 6/18/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 6/18/2024 Approved MEL KHACHATOURIAN
Verify Sprinkler Sign Off 6/18/2024 Approved MEL KHACHATOURIAN
Insulation 7/1/2024 Approved ASHLEY THOMPSON
Drywall Nailing 7/5/2024 Approved MEL KHACHATOURIAN
ELECTRICAL-Final 1/28/2025 Corrections Issued SEAN HAUPT
Final 1/28/2025 Corrections Issued SEAN HAUPT
HVAC-Final 1/28/2025 Corrections Issued SEAN HAUPT
PLUMBING-Final 1/28/2025 Corrections Issued SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 1/28/2025 SGSOV Approved SEAN HAUPT
Smoke Detectors 1/28/2025 Approved SEAN HAUPT
Final 3/18/2025 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 3/18/2025 Approved ASHLEY THOMPSON
Green Building Final 3/18/2025 Approved ASHLEY THOMPSON
METHANE-Barrier 3/18/2025 Approved ASHLEY THOMPSON
Service/Power Release 3/18/2025 Not Ready for Inspection ASHLEY THOMPSON
Final 3/24/2025 Not Ready for Inspection ARAM AVEDISIAN
Service/Power Release 3/24/2025 Not Ready for Inspection ARAM AVEDISIAN
Final 4/2/2025 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 4/2/2025 Approved ARAM AVEDISIAN