628-628 1/2 N BOYLE AVE 90033

Certificate Information: 628-628 1/2 N BOYLE AVE 90033

Application / Permit
22014-10000-03145
Plan Check / Job No.
B22LA12184
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan convert potion of existing attached garage into ADU in existing one story single family dewlling per WFPP (Attached ADU per Ordinance, LAMC 12.22 A.33(c) and (e))
Permit Issued
Issued on 7/28/2022
Issuing Office
Current Status
CofO Issued on 10/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/25/2022 APPLICANT
Assigned to Plan Check Engineer 7/1/2022 AUNG SOE
Corrections Issued 7/4/2022 AUNG SOE
Plan Check Approved 7/26/2022 AUNG SOE
Issued 7/28/2022 APPLICANT
CofO in Progress 9/20/2023 OSVALDO PARAMO
CofO in Progress 9/20/2023 OSVALDO PARAMO
No Progress 9/27/2023 SCOTT FINNILA
CofO in Progress 9/28/2023 SCOTT FINNILA
Permit Finaled 10/4/2023 DEROLD HAUFF
CofO Issued 10/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Clean Up Green Up Cleared 7/12/2022 RUBEN VASQUEZ
ZI Cleared 7/12/2022 RUBEN VASQUEZ
Tenant Habitability Plan Cleared 7/13/2022 MICHAEL SOTO
Address approval Cleared 7/14/2022 CINDY QI
Sewer availability Cleared 7/14/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 7/19/2022 CINDY QI
Grading Pre-Inspection Cleared 7/21/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/7/2022 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 12/19/2022 No Access for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 12/27/2022 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 4/11/2023 Approved OSVALDO PARAMO
HVAC-Rough 4/11/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 4/11/2023 Approved OSVALDO PARAMO
Wood Frame 4/11/2023 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 5/15/2023 Approved OSVALDO PARAMO
ELECTRICAL-Rough 5/15/2023 Approved OSVALDO PARAMO
MERV13>=Rough 5/15/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 5/15/2023 Approved OSVALDO PARAMO
Underground Mechanical 5/15/2023 Approved OSVALDO PARAMO
Insulation 6/5/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 6/5/2023 Approved OSVALDO PARAMO
Shower Pan 6/5/2023 Approved OSVALDO PARAMO
Drywall Nailing 6/15/2023 Approved RUBEN SALAS
Final 9/11/2023 Corrections Issued OSVALDO PARAMO
MERV13>=Final 9/11/2023 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/11/2023 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 9/11/2023 Approved OSVALDO PARAMO
Final 9/19/2023 OK to Issue CofO OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/19/2023 SGSOV Approved OSVALDO PARAMO