628 1/4 W 87TH ST 90044

Certificate Information: 628 1/4 W 87TH ST 90044

Application / Permit
22014-10000-03138
Plan Check / Job No.
B22LA12178
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT AND ADDITION NFPA 13D (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 9/6/2022
Issuing Office
Current Status
CofO Issued on 9/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2022 APPLICANT
Assigned to Plan Check Engineer 7/1/2022 AUNG SOE
Corrections Issued 7/2/2022 AUNG SOE
Plan Check Approved 8/22/2022 ADAM HEGAZI
Issued 9/6/2022 APPLICANT
CofO in Progress 9/18/2023 MICHAEL LEWIS
Permit Finaled 9/21/2023 DEROLD HAUFF
CofO Issued 9/21/2023 DEROLD HAUFF
Permit Finaled 9/21/2023 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 7/29/2022 DALIA MOKAYED
ZA Case Cleared 7/29/2022 DALIA MOKAYED
Address approval Cleared 8/2/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 8/2/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/4/2022 STEVE MELGAR
Sewer availability Cleared 8/4/2022 STEVE MELGAR

Contact Information

Architect Carrillo,, Jessie; Lic. No.: C32448 13006 PHILADELPHIA ST #506      WHITTIER, CA 90601
Contractor Owner-Builder       ,
Engineer Contreras,, Humberto; Lic. No.: C83240 10614 PARISE DR      WHITTIER, CA 90604

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/24/2022 Partial Approval LILIANA PORTILLO
Deputy Drilled-In Anchors 10/27/2022 Conditional Approval LILIANA PORTILLO
Footing/Foundation/Slab 10/31/2022 Corrections Issued LILIANA PORTILLO
Deputy Drilled-In Anchors 11/4/2022 Approved LILIANA PORTILLO
Footing/Foundation/Slab 11/4/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/30/2022 Approved LILIANA PORTILLO
Gas Test 11/30/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 11/30/2022 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 1/19/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 1/19/2023 Approved ALEJANDRO DE ARTOLA
Gas Test 1/19/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 1/19/2023 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 1/19/2023 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/19/2023 Partial Approval ALEJANDRO DE ARTOLA
Sewer 1/19/2023 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 2/8/2023 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 2/8/2023 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 2/15/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 2/15/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 2/21/2023 Approved LILIANA PORTILLO
Insulation 2/23/2023 Corrections Issued LILIANA PORTILLO
Drywall Nailing 2/28/2023 Approved LILIANA PORTILLO
Insulation 2/28/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 3/8/2023 Approved LILIANA PORTILLO
Gas Test 6/7/2023 Approved STUART CHAPMAN
Final 6/30/2023 Corrections Issued MICHAEL LEWIS
Gas Test 6/30/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 6/30/2023 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 6/30/2023 Corrections Issued MICHAEL LEWIS
Final 8/31/2023 Partial Inspection MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 8/31/2023 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 8/31/2023 Approved MICHAEL LEWIS
Final 9/15/2023 OK to Issue CofO MICHAEL LEWIS
HVAC-Final 9/15/2023 Approved MICHAEL LEWIS