6365 W 83RD ST 90045
Certificate Information: 6365 W 83RD ST 90045
- Application / Permit
- 22014-10000-03132
- Plan Check / Job No.
- B22LA12168
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: convert exisitng detached garage (441sf) into adu with addition per engineer details (1,200 SF max per Ordinance,LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 9/1/2023
- Issuing Office
- Current Status
- CofO Issued on 2/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2022 | AUNG SOE |
| Corrections Issued | 7/4/2022 | AUNG SOE |
| Applicant returned to address corrections | 11/30/2022 | HERNAN ARREOLA |
| Plan Check Approved | 12/25/2022 | AUNG SOE |
| Issued | 9/1/2023 | APPLICANT |
| CofO in Progress | 2/11/2025 | EVAN COOPER |
| Permit Finaled | 2/13/2025 | RICHARD STEINBACH |
| CofO Issued | 2/13/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/13/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/1/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/1/2022 | RIDWAN HARDY |
| Address approval | Cleared | 11/7/2022 | RAYMOND MUGAMBWA |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2022 | RAYMOND MUGAMBWA |
| Roof/Waste drainage to street | Cleared | 11/22/2022 | RAYMOND MUGAMBWA |
| Sewer availability | Cleared | 11/22/2022 | RAYMOND MUGAMBWA |
| Specific Plan | Cleared | 12/22/2022 | JOSHUA JONES |
Contact Information
| Contractor | J T C Startline Inc; Lic. No.: 1077653-B | 16388 COLIMA ROAD #107 HACIENDA HEIGHTS, CA 91745 |
| Engineer | Chen,, Junfei; Lic. No.: C85841 | 726 FAMILY TREE IRVINE, CA 92618 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/20/2023 | Corrections Issued | HERBERT GIRON |
| Sewer | 10/27/2023 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 11/17/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Underground Mechanical | 11/17/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 11/28/2023 | Approved | TEMISTOCLES CAAL |
| Deputy Drilled-In Anchors | 12/13/2023 | Conditional Approval | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 12/15/2023 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 12/15/2023 | Approved | TEMISTOCLES CAAL |
| Wood Frame | 3/15/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Deputy Wood Construction | 4/8/2024 | Conditional Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 4/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 4/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2024 | Partial Approval | TEMISTOCLES CAAL |
| Green Building Rough | 4/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 4/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Special/Order Compliance | 4/12/2024 | Partial Inspection | HERBERT GIRON |
| Pre-Inspection | 4/19/2024 | Partial Inspection | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 5/17/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 5/17/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 5/17/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 5/17/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 5/17/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 6/3/2024 | Partial Approval | TEMISTOCLES CAAL |
| Special/Order Compliance | 6/3/2024 | Partial Inspection | HERBERT GIRON |
| Insulation | 6/28/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 7/26/2024 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 9/5/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 9/13/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 1/10/2025 | Corrections Issued | MICHAEL ALLEN |
| Final | 1/10/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Green Building Final | 1/10/2025 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Final | 1/10/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 1/10/2025 | Corrections Issued | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 1/10/2025 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 1/10/2025 | Approved | MICHAEL ALLEN |
| Final | 1/21/2025 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 1/21/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 2/10/2025 | Approved | EVAN COOPER |
| Final | 2/10/2025 | OK to Issue CofO | EVAN COOPER |
| PLUMBING-Final | 2/10/2025 | Approved | EVAN COOPER |
| Service/Power Release | 2/10/2025 | Approved | EVAN COOPER |