2179 1/2 W 26TH PL 90018

Certificate Information: 2179 1/2 W 26TH PL 90018

Application / Permit
22014-10000-03131
Plan Check / Job No.
B22LA12166
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan PROPOSED 2ND STORY ADDITION ADU TO EXISTING GARAGE
Permit Issued
Issued on 8/17/2023
Issuing Office
Current Status
CofO Issued on 8/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2022 APPLICANT
Assigned to Plan Check Engineer 7/21/2022 CRYSTEL MAALOUF
Corrections Issued 8/1/2022 CRYSTEL MAALOUF
Quality Review Completed 8/2/2022 GARO TELMI
Applicant returned to address corrections 5/2/2023 CRYSTEL MAALOUF
Plan Check Approved 6/19/2023 CRYSTEL MAALOUF
Plan Check Approved 8/17/2023 CRYSTEL MAALOUF
Issued 8/17/2023 APPLICANT
Permit Finaled 8/22/2024 ADAM BURGESS
CofO Issued 8/22/2024 ADAM BURGESS
Permit Finaled 8/22/2024 ADAM BURGESS

Permit Application Clearance Information

Address approval Cleared 10/11/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 10/11/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 11/4/2022 AMAAN MALIK
Sewer availability Cleared 11/4/2022 AMAAN MALIK
HPOZ Cleared 5/16/2023 DANIEL MATA

Contact Information

Contractor Owner-Builder       ,
Engineer O'Brien,, Kathleen Anne; Lic. No.: C49498 1058 PACIFIC AVE      SIMI VALLEY, CA 93065

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/25/2023 Partial Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 10/23/2023 Corrections Issued JUSTIN HAWLEY
Footing/Foundation/Slab 10/23/2023 Not Ready for Inspection JUSTIN HAWLEY
Deputy Drilled-In Anchors 10/25/2023 Conditional Approval KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 10/26/2023 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 10/26/2023 Corrections Issued STUART CHAPMAN
METHANE-Barrier 10/26/2023 Approved STUART CHAPMAN
METHANE-Subgrade 10/26/2023 Approved STUART CHAPMAN
Deputy Reinf. Concrete 11/7/2023 Conditional Approval KATHRYN BUTTERWORTH
METHANE-Rough 12/5/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Wood Frame 12/5/2023 Corrections Issued KATHRYN BUTTERWORTH
METHANE-Rough 12/29/2023 Approved MARTIN TAVITIAN
Wood Frame 12/29/2023 Not Ready for Inspection MARTIN TAVITIAN
Wood Frame 1/10/2024 Partial Approval RICARDO ROBLES
Insulation 1/30/2024 Partial Approval LUIS CCAMACHO
Interior/Exterior Lathing 1/30/2024 Partial Approval LUIS CCAMACHO
Insulation 2/1/2024 Approved MARTIN TAVITIAN
Drywall Nailing 2/6/2024 Approved MARTIN TAVITIAN
Final 7/26/2024 Not Ready for Inspection DARRYL ARNOLD
Footing/Foundation/Slab 7/26/2024 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 7/26/2024 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 7/26/2024 Corrections Issued DARRYL ARNOLD
Wood Frame 7/26/2024 Approved DARRYL ARNOLD