1637 N MCDONALD AVE 90744

Certificate Information: 1637 N MCDONALD AVE 90744

Application / Permit
22014-10000-03121
Plan Check / Job No.
B22LA12125
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 8/23/2022
Issuing Office
Current Status
CofO Issued on 3/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 DANIEL YIP
Corrections Issued 7/1/2022 DANIEL YIP
Plan Check Approved 7/15/2022 DANIEL YIP
Issued 8/23/2022 APPLICANT
CofO in Progress 3/13/2024 EUGENE CASSIDY
Permit Finaled 3/13/2024 ANSON MAGLASANG
CofO Issued 3/13/2024 ANSON MAGLASANG
Permit Finaled 3/13/2024 ANSON MAGLASANG

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/6/2022 HUGO LOPEZ
Sewer availability Cleared 7/6/2022 HUGO LOPEZ
Clean Up Green Up Cleared 7/12/2022 NOAH MCCOY
Eng Process Fee Ord 176,300 Cleared 7/13/2022 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/25/2022 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/1/2022 Partial Approval EUGENE CASSIDY
Insulation 11/2/2022 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/7/2022 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 11/29/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 2/6/2023 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 2/6/2023 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 4/12/2023 Partial Approval EUGENE CASSIDY
Green Building Rough 4/12/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 4/12/2023 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 4/12/2023 Approved EUGENE CASSIDY
Insulation 4/17/2023 Approved EUGENE CASSIDY
Drywall Nailing 4/20/2023 Approved EUGENE CASSIDY
Green Building Rough 4/20/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 4/20/2023 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 5/9/2023 Approved EUGENE CASSIDY
Shower Pan 5/9/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/6/2023 Approved EUGENE CASSIDY
Final 9/6/2023 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 9/6/2023 Approved EUGENE CASSIDY
Green Building Final 9/6/2023 Not Ready for Inspection EUGENE CASSIDY
METHANE-Barrier 9/6/2023 Approved EUGENE CASSIDY
METHANE-Subgrade 9/6/2023 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/6/2023 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 9/6/2023 Not Ready for Inspection EUGENE CASSIDY
Final 2/16/2024 OK to Issue CofO EUGENE CASSIDY
Green Building Final 2/16/2024 Approved EUGENE CASSIDY
Smoke Detectors 2/16/2024 Approved EUGENE CASSIDY