4149 N ADLON PL 91436

Certificate Information: 4149 N ADLON PL 91436

Application / Permit
22014-10000-03107
Plan Check / Job No.
B22LA12113
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 4/27/2023
Issuing Office
Current Status
Issued on 4/27/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/22/2022 APPLICANT
Assigned to Plan Check Engineer 7/1/2022 DANIEL YIP
Corrections Issued 7/2/2022 DANIEL YIP
Plan Check Approved 7/19/2022 DANIEL YIP
No Progress 4/27/2023 DANIEL YIP
Plan Check Approved 4/27/2023 DANIEL YIP
Issued 4/27/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/2/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/5/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 7/6/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351
Engineer Garcia,, Francisco Diaz; Lic. No.: NA88029       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/9/2023 Partial Approval VINCENT HANLEY
PLUMBING-Rough 8/22/2023 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 8/24/2023 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 9/19/2023 Partial Approval VINCENT HANLEY
PLUMBING-Rough 10/24/2023 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 10/30/2023 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 12/13/2023 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 1/4/2024 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 1/10/2024 Partial Approval VINCENT HANLEY
Green Building Rough 1/10/2024 Not Ready for Inspection VINCENT HANLEY
Insulation 1/19/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/19/2024 Partial Approval VINCENT HANLEY
Masonry Wall/Backfill 1/22/2024 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 1/25/2024 Approved VINCENT HANLEY
Drywall Nailing 1/25/2024 Approved VINCENT HANLEY
Green Building Rough 1/25/2024 Approved VINCENT HANLEY
Shower Pan 3/5/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/8/2024 Approved VINCENT HANLEY