4149 N ADLON PL 91436
Certificate Information: 4149 N ADLON PL 91436
- Application / Permit
- 22014-10000-03107
- Plan Check / Job No.
- B22LA12113
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 4/27/2023
- Issuing Office
- Current Status
- Issued on 4/27/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2022 | DANIEL YIP |
| Corrections Issued | 7/2/2022 | DANIEL YIP |
| Plan Check Approved | 7/19/2022 | DANIEL YIP |
| No Progress | 4/27/2023 | DANIEL YIP |
| Plan Check Approved | 4/27/2023 | DANIEL YIP |
| Issued | 4/27/2023 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/2/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/5/2022 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 7/6/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 19145 MALABAR ST SANTA CLARITA, CA 91351 |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: NA88029 | , |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/9/2023 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 8/22/2023 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 8/24/2023 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 10/24/2023 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 10/30/2023 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2024 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/10/2024 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 1/10/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Insulation | 1/19/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 1/19/2024 | Partial Approval | VINCENT HANLEY |
| Masonry Wall/Backfill | 1/22/2024 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/25/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 1/25/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/25/2024 | Approved | VINCENT HANLEY |
| Shower Pan | 3/5/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/8/2024 | Approved | VINCENT HANLEY |