5501 W 77TH ST 90045

Certificate Information: 5501 W 77TH ST 90045

Application / Permit
22014-10000-03105
Plan Check / Job No.
B22LA12111
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: MAJOR ADDITION AND REMODEL TO (E) 1-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 12/5/2022
Issuing Office
Current Status
Issued on 12/5/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/22/2022 APPLICANT
Assigned to Plan Check Engineer 7/1/2022 DANIEL YIP
Corrections Issued 7/2/2022 DANIEL YIP
Applicant returned to address corrections 9/14/2022 DANIEL YIP
Plan Check Approved 9/28/2022 DANIEL YIP
Issued 12/5/2022 APPLICANT

Permit Application Clearance Information

Specific Plan Cleared 7/14/2022 NELSON RODRIGUEZ
Eng Process Fee Ord 176,300 Cleared 7/20/2022 JENSON LEE
Sewer availability Cleared 7/20/2022 JENSON LEE
Grading Pre-Inspection Cleared 8/5/2022 KIRK LINKLATER
Low Impact Development Cleared 8/22/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 8/24/2022 JENSON LEE
GPI Written Notices Cleared 9/28/2022 DANIEL YIP

Contact Information

Contractor Owner-Builder       ,
Engineer Nagovitsyn,, Evgeny; Lic. No.: C93527 17436 ARMINTA ST      NORTHRIDGE, CA 91325

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/14/2022 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 12/14/2022 Corrections Issued BOBBY KEY
Pre-Inspection 12/14/2022 Partial Inspection BOBBY KEY
Footing/Foundation/Slab 12/20/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/13/2023 Partial Approval BOBBY KEY
Special/Order Compliance 2/13/2023 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 3/30/2023 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 3/30/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 4/3/2023 Corrections Issued BOBBY KEY
Special/Order Compliance 4/3/2023 Corrections Issued BOBBY KEY
Wood Frame 4/3/2023 Conditional Approval BOBBY KEY
Deputy Wood Construction 4/6/2023 Conditional Approval JESUS PINEDA
Gas Test 4/6/2023 Approved JESUS PINEDA
ELECTRICAL-Rough 4/20/2023 Not Ready for Inspection BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 4/20/2023 Partial Approval BOBBY KEY
HVAC-Rough 4/20/2023 Not Ready for Inspection BOBBY KEY
Deputy Wood Construction 5/19/2023 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Corrections Issued HERBERT GIRON
Wood Frame 5/22/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/25/2023 Partial Approval RICHARD STEINBACH
Interior/Exterior Lathing 6/12/2023 No Access for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 6/23/2023 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 6/23/2023 Corrections Issued BOBBY KEY
Green Building Rough 6/23/2023 Not Ready for Inspection BOBBY KEY
HVAC-Rough 6/23/2023 Corrections Issued BOBBY KEY
MERV13>=Rough 6/23/2023 Approved BOBBY KEY
PLUMBING-Rough 6/23/2023 Approved BOBBY KEY
Verify Sprinkler Sign Off 6/23/2023 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 6/29/2023 Conditional Approval BOBBY KEY
ELECTRICAL-Rough 6/29/2023 Conditional Approval BOBBY KEY
HVAC-Rough 6/29/2023 Partial Approval BOBBY KEY
ELECTRICAL-Rough 7/10/2023 Approved BOBBY KEY
Insulation 7/10/2023 Conditional Approval BOBBY KEY
BUILDING-Rough-Frame 8/8/2023 Approved BOBBY KEY
Drywall Nailing 8/8/2023 Approved BOBBY KEY
Green Building Rough 8/8/2023 Approved BOBBY KEY
HVAC-Rough 8/8/2023 Not Ready for Inspection BOBBY KEY
Insulation 8/8/2023 Approved BOBBY KEY
Interior/Exterior Lathing 8/8/2023 Not Ready for Inspection BOBBY KEY
Shower Pan 8/8/2023 Corrections Issued BOBBY KEY
Verify Sprinkler Sign Off 8/8/2023 Approved BOBBY KEY
Interior/Exterior Lathing 8/11/2023 Approved HERBERT GIRON
Shower Pan 8/11/2023 Approved HERBERT GIRON
ELECTRICAL-Final 1/19/2024 Corrections Issued BOBBY KEY
Final 1/19/2024 Corrections Issued BOBBY KEY
Green Building Final 1/19/2024 Approved BOBBY KEY
HVAC-Final 1/19/2024 Corrections Issued BOBBY KEY
MERV13>=Final 1/19/2024 Not Ready for Inspection BOBBY KEY
PLUMBING-Final 1/19/2024 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 1/19/2024 SGSOV Not Required BOBBY KEY
Smoke Detectors 1/19/2024 Approved BOBBY KEY