7022-7024 N NESTLE AVE 91335

Certificate Information: 7022-7024 N NESTLE AVE 91335

Application / Permit
22014-10000-03084
Plan Check / Job No.
B22LA12012
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER STATE LAW. ENCLOSE COVERED PATIO TO LIVING AREA FOR THE SINGLE FAMLY DWELLING, ADD NEW DECK AT REAR OF BUILDING. ALL WORK DONE PER WFPP
Permit Issued
Issued on 10/17/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2022 APPLICANT
Assigned to Plan Check Engineer 6/23/2022 KHUONG TRUONG
Corrections Issued 6/25/2022 KHUONG TRUONG
Building Plans Picked Up 6/28/2022 APPLICANT
Applicant returned to address corrections 9/16/2022 FERNANDO FLORES
Applicant returned to address corrections 9/30/2022 LAWRENCE QUIRANTE
Plan Check Approved 10/14/2022 GEORGE ALVAREZ
Plan Check Approved 10/14/2022 GEORGE ALVAREZ
Issued 10/17/2022 APPLICANT
CofO in Progress 10/1/2025 ARUTYUN MADATYAN
Permit Finaled 10/7/2025 JOHN JANSON
CofO Issued 10/7/2025 JOHN JANSON
Permit Finaled 10/7/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/13/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/18/2022 CARLOS AGUILERA
Sewer availability Cleared 7/18/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/30/2022 Partial Approval SEAN WIRCH
Excavation/Setback/Form/Re-Bar 12/7/2022 Corrections Issued DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 12/13/2022 Corrections Issued JEFFREY BULL
Footing/Foundation/Slab 12/13/2022 Not Ready for Inspection JEFFREY BULL
Grounding or Bonding 12/13/2022 Not Ready for Inspection JEFFREY BULL
Pre-Inspection 12/13/2022 Not Ready for Inspection JEFFREY BULL
Pre-Inspection 9/25/2023 Approved JEFFREY BULL
ELECTRICAL-Rough 10/6/2023 Not Ready for Inspection JEFFREY HARTLINE
Footing/Foundation/Slab 10/6/2023 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 10/6/2023 Partial Approval JEFFREY HARTLINE
Deputy Drilled-In Anchors 10/19/2023 Conditional Approval JEFFREY BULL
BUILDING-Rough-Frame 10/24/2023 Not Ready for Inspection JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Partial Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 1/23/2024 Partial Approval JEFFREY BULL
ELECTRICAL-Rough 2/13/2024 Approved JEFFREY BULL
Insulation 2/13/2024 Not Ready for Inspection JEFFREY BULL
Interior/Exterior Lathing 2/13/2024 Partial Approval JEFFREY BULL
PLUMBING-Rough 2/13/2024 Approved JEFFREY BULL
Insulation 3/13/2024 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 3/13/2024 Not Ready for Inspection JEFFREY PARD
Insulation 3/19/2024 Approved JEFFREY BULL
PLUMBING-Final 3/19/2024 Approved JEFFREY BULL
Shower Pan 3/19/2024 Not Ready for Inspection JEFFREY BULL
BUILDING-Rough-Frame 4/8/2024 Approved JEFFREY BULL
Gas Test 4/8/2024 Approved JEFFREY BULL
Green Building Rough 4/8/2024 Approved JEFFREY BULL
PLUMBING-Rough 4/8/2024 Approved JEFFREY BULL
Shower Pan 4/8/2024 Not Ready for Inspection JEFFREY BULL
PLUMBING-Rough 4/10/2024 Approved JEFFREY BULL
Shower Pan 4/10/2024 Approved JEFFREY BULL
Final 10/4/2024 Not Ready for Inspection JEFFREY BULL
Green Building Final 10/4/2024 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 10/4/2024 SGSOV Approved JEFFREY BULL
Smoke Detectors 10/4/2024 Not Ready for Inspection JEFFREY BULL
ELECTRICAL-Rough 12/4/2024 Corrections Issued ARUTYUN MADATYAN
ELECTRICAL-Rough 12/5/2024 Partial Approval ARUTYUN MADATYAN
Service/Power Release 12/5/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 4/29/2025 Not Ready for Inspection ARUTYUN MADATYAN
Final 4/29/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Final 4/29/2025 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Final 4/29/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Final 4/29/2025 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 4/29/2025 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Final 5/2/2025 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Final 5/2/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Final 5/2/2025 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Final 7/3/2025 Corrections Issued JUAN ALVARADO
Final 7/3/2025 Corrections Issued JUAN ALVARADO
Green Building Final 7/3/2025 Approved JUAN ALVARADO
HVAC-Final 7/3/2025 Not Ready for Inspection JUAN ALVARADO
PLUMBING-Final 7/3/2025 Approved JUAN ALVARADO
Smoke Detectors 7/3/2025 Approved JUAN ALVARADO
Final 8/22/2025 No Access for Inspection ARUTYUN MADATYAN
Final 9/3/2025 Corrections Issued ARUTYUN MADATYAN
ELECTRICAL-Final 10/1/2025 Approved ARUTYUN MADATYAN
Final 10/1/2025 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 10/1/2025 Approved ARUTYUN MADATYAN