15749 W GREENLEAF ST 91436

Certificate Information: 15749 W GREENLEAF ST 91436

Application / Permit
22014-10000-03070
Plan Check / Job No.
B22LA11912
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Enclosure and interior remodel to an existing one-story single.
Permit Issued
Issued on 7/15/2022
Issuing Office
Current Status
Permit Finaled on 3/31/2023

Permit Application Status History

Submitted 6/20/2022 APPLICANT
Assigned to Plan Check Engineer 6/21/2022 JOE VO
Corrections Issued 6/22/2022 JOE VO
Plan Check Approved 7/9/2022 JOE VO
Issued 7/15/2022 APPLICANT
Permit Finaled 3/30/2023 VINCENT HANLEY

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/28/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 6/28/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 6/28/2022 JOSE DUARTE-DIAZ
Public Works-Open Permits Cleared 6/28/2022 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 6/28/2022 JOSE DUARTE-DIAZ
Grading Pre-Inspection Cleared 7/6/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: NA53210       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/20/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 9/20/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 10/3/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 10/3/2022 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 10/4/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/5/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Partial Approval DAVID SANDOVAL
BUILDING-Rough-Frame 11/16/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/16/2022 Approved VINCENT HANLEY
Wood Frame 11/16/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 11/22/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 11/22/2022 Approved VINCENT HANLEY
Green Building Rough 11/22/2022 Approved VINCENT HANLEY
HVAC-Rough 11/22/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 11/22/2022 Approved VINCENT HANLEY
PLUMBING-Rough 11/22/2022 Approved VINCENT HANLEY
Drywall Nailing 12/2/2022 Approved VINCENT HANLEY
Final 3/30/2023 Permit Finaled VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/30/2023 SGSOV Approved VINCENT HANLEY
Smoke Detectors 3/30/2023 Approved VINCENT HANLEY