6241 W MARYLAND DR 90048

Certificate Information: 6241 W MARYLAND DR 90048

Application / Permit
22014-10000-03064
Plan Check / Job No.
B22LA11908
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan (N) 81 S.F. BEDROOM & BATH ADDITION TO (E) S.F.R., TYPE VB CONSTRUCTION
Permit Issued
Issued on 8/31/2022
Issuing Office
Current Status
CofO Issued on 6/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2022 APPLICANT
Assigned to Plan Check Engineer 6/22/2022 JOSEPH RAFOLS
Corrections Issued 6/23/2022 JOSEPH RAFOLS
Plan Check Approved 6/28/2022 JOSEPH RAFOLS
Issued 8/31/2022 APPLICANT
CofO in Progress 4/7/2023 JEREMY TODD
CofO in Progress 4/12/2023 JEREMY TODD
CofO in Progress 4/26/2023 JEREMY TODD
Permit Finaled 6/8/2023 DANIEL ORRANTE
CofO Issued 6/8/2023 DANIEL ORRANTE
Permit Finaled 6/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/27/2022 CINDY QI
Roof/Waste drainage to street Cleared 6/27/2022 CINDY QI
Sewer availability Cleared 6/27/2022 CINDY QI

Contact Information

Architect Espinosa,, Mauricio; Lic. No.: NA34617       ,
Contractor E S V Prime Construction Specialists Inc; Lic. No.: 861628-B       ,
Contractor E S V Prime Construction Specialists; Lic. No.: 861628-B       ,

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/20/2022 Corrections Issued EVAN COOPER
METHANE-Barrier 9/20/2022 Approved EVAN COOPER
METHANE-Subgrade 9/20/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 9/27/2022 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 9/27/2022 Approved EVAN COOPER
METHANE-Rough 9/27/2022 Approved EVAN COOPER
PLUMBING-Rough 9/27/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 11/9/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 11/9/2022 Approved GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 11/9/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 11/9/2022 Approved GERMAN RODRIGUEZ MENDOZA
Wood Frame 11/9/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 11/18/2022 Approved ASHLEY THOMPSON
HVAC-Rough 11/18/2022 Corrections Issued ASHLEY THOMPSON
Interior/Exterior Lathing 1/24/2023 Approved JEREMY TODD
Wood Frame 1/24/2023 Approved JEREMY TODD
Insulation 1/25/2023 Approved JEREMY TODD
Drywall Nailing 1/27/2023 Approved JEREMY TODD
Interior/Exterior Lathing 1/30/2023 Approved JEREMY TODD
Shower Pan 1/30/2023 Approved JEREMY TODD
BUILDING-Rough-Frame 4/5/2023 Approved JEREMY TODD
ELECTRICAL-Final 4/5/2023 Approved JEREMY TODD
Final 4/5/2023 Not Ready for Inspection JEREMY TODD
Footing/Foundation/Slab 4/5/2023 Approved JEREMY TODD
HVAC-Final 4/5/2023 Approved JEREMY TODD
PLUMBING-Final 4/5/2023 Approved JEREMY TODD
SGSOV-Seismic Gas S/O Valve 4/5/2023 SGSOV Approved JEREMY TODD
Smoke Detectors 4/5/2023 Approved JEREMY TODD
Special/Order Compliance 4/12/2023 Corrections Issued JEREMY TODD
Final 4/25/2023 OK to Issue CofO JEREMY TODD