3994 S ORANGE DR 90008

Certificate Information: 3994 S ORANGE DR 90008

Application / Permit
22014-10000-03050
Plan Check / Job No.
B22LA11831
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan 1- New 1-story front addition of 449 sq.ft. 2.-New front porch of 22 sq.ft 3.-Interior remodel of e) 1-story S.F.R.
Permit Issued
Issued on 8/6/2022
Issuing Office
Current Status
Issued on 8/6/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/20/2022 APPLICANT
Assigned to Plan Check Engineer 6/22/2022 JOSEPH RAFOLS
Corrections Issued 6/23/2022 JOSEPH RAFOLS
Plan Check Approved 8/2/2022 JOSEPH RAFOLS
Issued 8/6/2022 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/7/2022 WALLIE JONG
Sewer availability Cleared 7/7/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/12/2022 WALLIE JONG
Grading Pre-Inspection Cleared 7/12/2022 MATTHEW JENKINS

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: NA77737       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/25/2022 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 10/25/2022 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 11/2/2022 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 11/2/2022 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 11/14/2022 No Access for Inspection ANTHONY EGSON
Footing/Foundation/Slab 11/14/2022 No Access for Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 11/17/2022 Approved ANTHONY EGSON
Footing/Foundation/Slab 11/17/2022 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 11/21/2022 Approved ANTHONY EGSON
Footing/Foundation/Slab 11/21/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 1/9/2023 No Access for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 1/12/2023 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 1/17/2023 Corrections Issued ANTHONY EGSON
Deputy Wood Construction 1/19/2023 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 1/24/2023 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 1/26/2023 Partial Approval ANTHONY EGSON
PLUMBING-Rough 1/26/2023 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 2/2/2023 Approved ANTHONY EGSON
ELECTRICAL-Rough 2/8/2023 Approved SCOTT FINNILA
BUILDING-Rough-Frame 2/14/2023 Approved SABAS ALONSO
Green Building Rough 2/14/2023 Approved SABAS ALONSO
HVAC-Rough 2/14/2023 Approved SABAS ALONSO
Shower Pan 2/14/2023 Partial Approval SABAS ALONSO
Wood Frame 2/14/2023 Approved SABAS ALONSO
Insulation 2/17/2023 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 2/17/2023 Partial Approval STUART CHAPMAN
Insulation 2/24/2023 Not Ready for Inspection ANTHONY EGSON
Interior/Exterior Lathing 2/24/2023 Approved ANTHONY EGSON
Insulation 2/27/2023 Approved ANTHONY EGSON
Drywall Nailing 3/20/2023 Approved ANTHONY EGSON
PLUMBING-Final 5/4/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 5/24/2023 Corrections Issued ANTHONY EGSON