4861 N WIOTA ST 90041

Certificate Information: 4861 N WIOTA ST 90041

Application / Permit
22014-10000-03041
Plan Check / Job No.
B22LA11819
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel and addition to an existing single family dwelling. New addition to include an attached carport. NFPA 13D sprinklers throughout
Permit Issued
Issued on 1/6/2023
Issuing Office
Current Status
CofO Issued on 2/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/27/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 JAD BASMA
Corrections Issued 7/22/2022 JAD BASMA
Quality Review Completed 7/29/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 11/1/2022 JAD BASMA
Applicant returned to address corrections 11/7/2022 JAD BASMA
Plan Check Approved 11/15/2022 JAD BASMA
No Progress 11/15/2022 JAD BASMA
Plan Check Approved 11/15/2022 JAD BASMA
No Progress 12/16/2022 JAD BASMA
No Progress 12/19/2022 JAD BASMA
Plan Check Approved 1/6/2023 JAD BASMA
Issued 1/6/2023 APPLICANT
CofO in Progress 2/8/2024 CRAIG VAUGHAN
Permit Finaled 2/19/2024 DEROLD HAUFF
CofO Issued 2/19/2024 DEROLD HAUFF
Permit Finaled 2/19/2024 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 9/24/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 9/24/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 9/24/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 9/24/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 9/24/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 9/24/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 10/17/2022 ABEL CASILLAS
Sewer availability Cleared 10/17/2022 ABEL CASILLAS
Low Impact Development Cleared 10/28/2022 ANTHONY VARGAS
GPI Written Notices Cleared 11/1/2022 JAD BASMA
Grading Pre-Inspection Cleared 11/1/2022 JAD BASMA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/11/2023 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 2/7/2023 Not Ready for Inspection RUBEN SALAS
Footing/Foundation/Slab 2/7/2023 Conditional Approval RUBEN SALAS
Piling/Pier/Caisson 2/7/2023 Corrections Issued RUBEN SALAS
Excavation/Setback/Form/Re-Bar 2/15/2023 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 2/15/2023 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 2/21/2023 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/7/2023 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 3/30/2023 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/30/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 3/30/2023 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/5/2023 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/17/2023 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 4/17/2023 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 5/1/2023 Partial Approval ALIZAH MAYAGOITIA
Wood Frame 5/1/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/11/2023 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 5/18/2023 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 5/19/2023 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 6/6/2023 Corrections Issued CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Corrections Issued JEFFREY MEAD
PLUMBING-Rough 6/14/2023 No Access for Inspection JEFFREY MEAD
BUILDING-Rough-Frame 6/22/2023 Not Ready for Inspection BRIAN SULLIVAN
Deputy Wood Construction 6/22/2023 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 6/22/2023 Corrections Issued BRIAN SULLIVAN
PLUMBING-Rough 6/22/2023 Not Ready for Inspection BRIAN SULLIVAN
Wood Frame 6/22/2023 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 6/30/2023 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Rough 6/30/2023 Not Ready for Inspection JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 6/30/2023 Not Ready for Inspection JEFFREY MEAD
HVAC-Rough 6/30/2023 Not Ready for Inspection JEFFREY MEAD
Interior/Exterior Lathing 6/30/2023 Not Ready for Inspection JEFFREY MEAD
PLUMBING-Rough 6/30/2023 Not Ready for Inspection JEFFREY MEAD
Wood Frame 6/30/2023 Corrections Issued JEFFREY MEAD
ELECTRICAL-Rough 7/7/2023 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 7/7/2023 Partial Approval CRAIG VAUGHAN
HVAC-Rough 7/7/2023 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 7/7/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 7/7/2023 Partial Approval CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 7/7/2023 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 7/14/2023 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 7/14/2023 Corrections Issued CRAIG VAUGHAN
Interior/Exterior Lathing 7/14/2023 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 7/17/2023 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 7/17/2023 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 7/17/2023 Not Ready for Inspection CRAIG VAUGHAN
Insulation 8/14/2023 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 8/16/2023 Approved CRAIG VAUGHAN
HVAC-Rough 8/16/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 8/16/2023 Approved CRAIG VAUGHAN
Wood Frame 8/16/2023 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 8/17/2023 Approved CRAIG VAUGHAN
Drywall Nailing 8/17/2023 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 8/17/2023 Approved CRAIG VAUGHAN
HVAC-Rough 8/17/2023 Approved CRAIG VAUGHAN
Insulation 8/17/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 8/17/2023 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 8/17/2023 Approved CRAIG VAUGHAN
Drywall Nailing 8/22/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 8/22/2023 Approved CRAIG VAUGHAN
Shower Pan 8/22/2023 Approved CRAIG VAUGHAN
Grounding or Bonding 9/19/2023 No Access for Inspection ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 10/12/2023 SGSOV Not Ready ROY SPAULDING
Final 11/15/2023 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 11/15/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/15/2023 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 11/15/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Final 12/4/2023 Corrections Issued CRAIG VAUGHAN
Final 12/4/2023 Corrections Issued CRAIG VAUGHAN
Gas Test 12/4/2023 Approved CRAIG VAUGHAN
HVAC-Final 12/4/2023 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 12/4/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 12/4/2023 SGSOV Approved CRAIG VAUGHAN
ELECTRICAL-Final 1/19/2024 Corrections Issued CRAIG VAUGHAN
Enclosure/Fence 1/19/2024 Approved CRAIG VAUGHAN
Final 1/19/2024 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Final 1/19/2024 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 1/25/2024 Approved CRAIG VAUGHAN
Final 1/25/2024 Corrections Issued CRAIG VAUGHAN
HVAC-Final 1/25/2024 Approved CRAIG VAUGHAN
Final 2/6/2024 OK to Issue CofO CRAIG VAUGHAN