10529 N GREENBURN AVE 91040
Certificate Information: 10529 N GREENBURN AVE 91040
- Application / Permit
- 22014-10000-03019
- Plan Check / Job No.
- B22LA11742
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO (N) ADU AND ADDITION (800 SF max New Construction per State Law,CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g))
- Permit Issued
- Issued on 8/11/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2022 | AUNG SOE |
| Corrections Issued | 6/23/2022 | AUNG SOE |
| Building Plans Picked Up | 6/24/2022 | APPLICANT |
| Applicant returned to address corrections | 7/8/2022 | ADAM HEGAZI |
| Plan Check Approved | 8/9/2022 | DANIEL SANJUAN |
| Issued | 8/11/2022 | APPLICANT |
| CofO in Progress | 7/14/2023 | DAVID ANDERSON |
| Permit Finaled | 8/16/2023 | RUBEN SALAS |
| CofO Issued | 8/16/2023 | RUBEN SALAS |
| Permit Finaled | 8/16/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/25/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/27/2022 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 6/30/2022 | ALEXANDER HELFER |
| Specific Plan | Cleared | 7/1/2022 | SARAH HOUNSELL |
| Low Impact Development | Cleared | 7/26/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 8/4/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/19/2022 | Partial Approval | MATTHEW NELSON |
| Underground Mechanical | 8/19/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 9/21/2022 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2022 | Partial Approval | MATTHEW NELSON |
| Deputy Wood Construction | 10/17/2022 | Conditional Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Approved | MATTHEW NELSON |
| HVAC-Rough | 10/24/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 10/24/2022 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 10/24/2022 | Approved | MATTHEW NELSON |
| Shower Pan | 10/24/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/31/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 10/31/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 10/31/2022 | Approved | MATTHEW NELSON |
| HVAC-Rough | 10/31/2022 | Approved | MATTHEW NELSON |
| Insulation | 11/4/2022 | Approved | MATTHEW NELSON |
| Drywall Nailing | 11/7/2022 | Approved | MATTHEW NELSON |
| Underground Mechanical | 2/15/2023 | Partial Approval | WILLIAM WREN |
| Gas Test | 3/10/2023 | Approved | WILLIAM WREN |
| Underground Mechanical | 3/31/2023 | Approved | WILLIAM WREN |
| Final | 6/27/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 6/27/2023 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 6/27/2023 | SGSOV Approved | WILLIAM WREN |
| Smoke Detectors | 6/27/2023 | Approved | WILLIAM WREN |
| HVAC-Final | 7/3/2023 | Corrections Issued | WILLIAM WREN |
| HVAC-Final | 7/10/2023 | Approved | DAVID ANDERSON |
| Final | 7/13/2023 | OK to Issue CofO | DAVID ANDERSON |