1638 W 256TH ST 90710

Certificate Information: 1638 W 256TH ST 90710

Application / Permit
22014-10000-03013
Plan Check / Job No.
B22LA11667
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. NEW ACCESSORY DWELLING UNIT ADDITION TO (E) DETACHED GARAGE PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 7/16/2022
Issuing Office
Current Status
CofO Issued on 7/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 KEVIN MORALES
Corrections Issued 6/27/2022 KEVIN MORALES
Plan Check Approved 7/14/2022 KEVIN MORALES
Issued 7/16/2022 APPLICANT
CofO in Progress 7/19/2023 EUGENE CASSIDY
Permit Finaled 7/24/2023 ANSON MAGLASANG
CofO Issued 7/24/2023 ANSON MAGLASANG
Permit Finaled 7/24/2023 ANSON MAGLASANG

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/5/2022 ERIK BEASLEY
Address approval Cleared 7/6/2022 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 7/6/2022 ERIK BEASLEY
Sewer availability Cleared 7/11/2022 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Lionel Jesus; Lic. No.: S4653 24702 NARBONNE AVE      LOMITA, CA 90717

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/3/2022 Partial Approval EUGENE CASSIDY
METHANE-Barrier 11/3/2022 Approved EUGENE CASSIDY
METHANE-Subgrade 11/3/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 11/22/2022 Partial Approval EUGENE CASSIDY
METHANE-Rough 11/22/2022 Approved EUGENE CASSIDY
Footing/Foundation/Slab 11/29/2022 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 1/23/2023 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 1/24/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 2/23/2023 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 3/20/2023 Approved EUGENE CASSIDY
HVAC-Rough 3/20/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 3/20/2023 Approved EUGENE CASSIDY
Wood Frame 3/20/2023 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 3/22/2023 Approved EUGENE CASSIDY
Insulation 3/22/2023 Approved EUGENE CASSIDY
Drywall Nailing 3/28/2023 Partial Approval EUGENE CASSIDY
Shower Pan 4/19/2023 Approved EUGENE CASSIDY
Service/Power Release 5/17/2023 Not Ready for Inspection EUGENE CASSIDY
Drywall Nailing 5/22/2023 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 5/22/2023 Not Ready for Inspection EUGENE CASSIDY
Final 5/22/2023 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 5/22/2023 Approved EUGENE CASSIDY
HVAC-Final 5/22/2023 Approved EUGENE CASSIDY
PLUMBING-Final 5/22/2023 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 5/22/2023 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 5/22/2023 Approved EUGENE CASSIDY
Drywall Nailing 6/2/2023 Approved EUGENE CASSIDY
ELECTRICAL-Final 6/2/2023 Approved EUGENE CASSIDY
Final 6/2/2023 Corrections Issued EUGENE CASSIDY
HVAC-Final 6/2/2023 Approved EUGENE CASSIDY
PLUMBING-Final 6/2/2023 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/2/2023 SGSOV Approved EUGENE CASSIDY
Final 7/3/2023 OK to Issue CofO EUGENE CASSIDY