1154 W 67TH ST 90044

Certificate Information: 1154 W 67TH ST 90044

Application / Permit
22014-10000-03010
Plan Check / Job No.
B22LA11664
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan MAJOR REMODEL OF (E) SFD WITH ADDITION AT THE FRONT. FIRE SPRINKLER NFPA-13D THROUGHT.
Permit Issued
Issued on 5/17/2023
Issuing Office
Current Status
CofO Issued on 5/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 FARSHAD ALIMOHAMADI
Corrections Issued 6/24/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 7/22/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 8/16/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 9/21/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 11/15/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 11/23/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 11/30/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/2/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 12/7/2022 FARSHAD ALIMOHAMADI
Issued 5/17/2023 APPLICANT
CofO in Progress 5/5/2026 SABAS ALONSO
Permit Finaled 5/8/2026 DEROLD HAUFF
CofO Issued 5/8/2026 DEROLD HAUFF
Permit Finaled 5/8/2026 DEROLD HAUFF

Permit Application Clearance Information

Permit Cleared 7/22/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/25/2022 JEANIE LAM
Trees in Parkway Cleared 8/5/2022 ADALBERTO VERA
Low Impact Development Cleared 9/6/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 9/15/2022 AMAAN MALIK
Construction near power lines Cleared 11/21/2022 RIDWAN HARDY

Contact Information

Contractor Raw Development Inc; Lic. No.: 989611-B       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/29/2024 Corrections Issued RONNIE MINDANAO
Footing/Foundation/Slab 2/2/2024 Not Ready for Inspection RONNIE MINDANAO
Deputy Wood Construction 8/18/2025 Conditional Approval BARRY HACHE
BUILDING-Rough-Frame 4/1/2026 Approved BARRY HACHE
Footing/Foundation/Slab 4/1/2026 Approved BARRY HACHE
SGSOV-Seismic Gas S/O Valve 4/1/2026 SGSOV Not Required BARRY HACHE
Smoke Detectors 4/1/2026 Approved BARRY HACHE
Final 4/14/2026 Corrections Issued RAUL BARAJAS
Final 5/4/2026 OK to Issue CofO SABAS ALONSO
Service/Power Release 5/4/2026 Approved SABAS ALONSO