2244 N RIDGEMONT DR 90046
Certificate Information: 2244 N RIDGEMONT DR 90046
- Application / Permit
- 22014-10000-02999
- Plan Check / Job No.
- B22LA11568
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW LIVING ROOM ADDITION TO SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 1/20/2023
- Issuing Office
- Valley
- Current Status
- Issued on 1/20/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | JAD BASMA |
| Corrections Issued | 7/29/2022 | JAD BASMA |
| Quality Review Completed | 8/5/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 8/8/2022 | APPLICANT |
| Plan Check Approved | 1/12/2023 | JAD BASMA |
| Issued | 1/20/2023 | APPLICANT |
Permit Application Clearance Information
| Private street | Cleared | 9/21/2022 | MARC WOERSCHING |
| BHO/Hillside ordinance | Cleared | 9/24/2022 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 9/24/2022 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 9/24/2022 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 9/24/2022 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 9/24/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 9/27/2022 | SAUL GARCIA |
| Hydrant and Access approval | Cleared | 10/11/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 12/22/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 12/22/2022 | CINDY QI |
| GPI Written Notices | Cleared | 1/12/2023 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 1/12/2023 | JAD BASMA |
Contact Information
| Contractor | Doobek Builders; Lic. No.: 980653-B | 5308 DERRY AVE I-101, 102 AGOURA HILLS, CA 91301 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 3/28/2023 | Corrections Issued | RAUL BARAJAS |
| Pre-Inspection | 3/28/2023 | Partial Inspection | RAUL BARAJAS |
| Piling/Pier/Caisson | 4/3/2023 | Partial Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 5/1/2023 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/1/2023 | Approved | RAUL BARAJAS |
| Pre-Inspection | 5/1/2023 | Approved | RAUL BARAJAS |
| Deputy Reinf. Concrete | 5/3/2023 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2023 | Corrections Issued | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2023 | Partial Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 7/14/2023 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 7/14/2023 | Approved | RAUL BARAJAS |
| Green Building Rough | 7/14/2023 | Approved | RAUL BARAJAS |
| HVAC-Rough | 7/14/2023 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 7/14/2023 | Approved | RAUL BARAJAS |
| Insulation | 7/27/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 7/27/2023 | Approved | RAUL BARAJAS |
| Drywall Nailing | 8/4/2023 | Approved | RAUL BARAJAS |
| HVAC-Rough | 8/4/2023 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 9/26/2023 | Approved | RAUL BARAJAS |
| Final | 9/26/2023 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 9/26/2023 | Approved | RAUL BARAJAS |
| HVAC-Final | 9/26/2023 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 9/26/2023 | Approved | RAUL BARAJAS |
| Final | 11/8/2023 | Conditional Approval | STUART CHAPMAN |