1371 S BEVERLY GLEN BLVD Units 1-26 90024

Certificate Information: 1371 S BEVERLY GLEN BLVD Units 1-26 90024

Application / Permit
22014-10000-02997
Plan Check / Job No.
B22LA11566
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
eplan CONVERT EXISTING OFFICE AND PORTION OF LOBBY OF AN EXISTING 24-UNIT APARTMENT BUILDING IN TO TWO ADUs PER STATE LAW CA Govt. Code 65852.2(e)(1)(C) . THE EXISTING APARTMENT IS 3-STORY TYPE VA OVER TYPE IA ON GRADE GARAGE.
Permit Issued
Issued on 5/2/2023
Issuing Office
Current Status
CofO Issued on 1/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2022 APPLICANT
Assigned to Plan Check Engineer 7/21/2022 QUAN NGHIEM
Corrections Issued 8/3/2022 QUAN NGHIEM
Quality Review Completed 8/11/2022 CHAD DOI
Applicant returned to address corrections 12/5/2022 QUAN NGHIEM
Applicant returned to address corrections 2/22/2023 QUAN NGHIEM
Plan Check Approved 2/22/2023 QUAN NGHIEM
Issued 5/2/2023 APPLICANT
CofO in Progress 1/17/2024 PAUL DAVIDSON
Permit Finaled 1/18/2024 DAVID TSAU
CofO Issued 1/18/2024 DAVID TSAU
Permit Finaled 1/18/2024 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 8/22/2022 CATHERINE ADROVER
Sewer availability Cleared 8/22/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 8/29/2022 CATHERINE ADROVER
Specific Plan Cleared 8/29/2022 KEVIN FULTON
Specific Plan Cleared 9/7/2022 EDUARDO HERMOSO
Green Code Cleared 9/8/2022 AARON COSTA
DAS Clearance Cleared 10/15/2022 ELIZABETH TOMS
Fire Marshal Fire Life Safety Cleared 11/8/2022 WILLIAM JOHNS

Contact Information

Architect Suayan,, Rey D; Lic. No.: C37726 11309 RASMUSSEN COURT      RIVERSIDE, CA 92505
Contractor Working Hands Builders Inc; Lic. No.: 1059742-B 22778 CASS AVENUE      WOODLAND HILLS, CA 91364
Contractor Z And J Manufacturing Group Inc; Lic. No.: 1059742-B 22778 CASS AVENUE      WOODLAND HILLS, CA 91364

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/31/2023 Approved PAUL DAVIDSON
Light Gage Steel Frame 7/10/2023 Approved MICHAEL PETRUSKO
METHANE-Rough 7/10/2023 Conditional Approval MICHAEL PETRUSKO
Drywall Nailing 7/25/2023 Approved MICHAEL PETRUSKO
Wood Frame 7/25/2023 Conditional Approval MICHAEL PETRUSKO
METHANE-Final 12/29/2023 Approved PAUL DAVIDSON
METHANE-Rough 12/29/2023 Approved PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 12/29/2023 SGSOV Not Ready PAUL DAVIDSON
Final 1/4/2024 Partial Inspection PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 1/4/2024 SGSOV Approved PAUL DAVIDSON
Smoke Detectors 1/4/2024 Approved PAUL DAVIDSON
Wood Frame 1/4/2024 Approved PAUL DAVIDSON
Final 1/17/2024 OK to Issue CofO PAUL DAVIDSON
Reinforced Concrete Frame 1/17/2024 Approved PAUL DAVIDSON