312 S WILLAMAN DR 1-25 90048

Certificate Information: 312 S WILLAMAN DR 1-25 90048

Application / Permit
22014-10000-02986
Plan Check / Job No.
B22LA11550
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
eplan Convert existing unused office into an ADU PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 5/2/2023
Issuing Office
Current Status
CofO Issued on 11/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 SERGIO GUTIERREZ
Corrections Issued 7/20/2022 SERGIO GUTIERREZ
Quality Review Completed 7/22/2022 RODOLFO ARIAS
Applicant returned to address corrections 1/12/2023 SERGIO GUTIERREZ
Plan Check Approved 3/2/2023 SERGIO GUTIERREZ
Issued 5/2/2023 APPLICANT
CofO in Progress 11/27/2023 ALFREDO LOPEZ
Permit Finaled 11/27/2023 ERNESTO CORRAL
CofO Issued 11/27/2023 ERNESTO CORRAL
Permit Finaled 11/27/2023 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 8/19/2022 ELAINE LEI
Sewer availability Cleared 8/19/2022 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 8/23/2022 ELAINE LEI
Tenant Habitability Plan Cleared 8/25/2022 MICHAEL SOTO
Green Code Cleared 9/8/2022 AARON COSTA
Hydrant and Access approval Cleared 9/28/2022 KURT CORRAL
DAS Clearance Cleared 10/14/2022 ELIZABETH TOMS
Fire Marshal Fire Life Safety Cleared 12/7/2022 DOMINIQUE MEDINA

Contact Information

Architect Suayan,, Rey D; Lic. No.: C37726 11309 RASMUSSEN COURT      RIVERSIDE, CA 92505
Architect Suayan,, Rey D; Lic. No.: NA37726       ,
Contractor Working Hands Builders Inc; Lic. No.: 1059742-B       ,
Contractor Z And J Manufacturing Group Inc; Lic. No.: 1059742-B       ,

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 7/11/2023 Partial Inspection JEROME BLACKWOOD
Pre-Inspection 7/11/2023 Partial Inspection JEROME BLACKWOOD
Drywall Nailing 7/20/2023 Not Ready for Inspection JEROME BLACKWOOD
Light Gage Steel Frame 8/16/2023 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 8/21/2023 Not Ready for Inspection JEROME BLACKWOOD
Light Gage Steel Frame 8/22/2023 Partial Approval JEROME BLACKWOOD
Insulation 8/23/2023 Partial Approval JEROME BLACKWOOD
Drywall Nailing 8/30/2023 Partial Approval JEROME BLACKWOOD
Final 10/26/2023 Conditional Approval JEROME BLACKWOOD
METHANE-Final 10/26/2023 Approved JEROME BLACKWOOD
METHANE-Rough 10/26/2023 Approved JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 10/26/2023 SGSOV Approved JEROME BLACKWOOD
Smoke Detectors 10/26/2023 Approved JEROME BLACKWOOD
Wood Frame 10/26/2023 Approved JEROME BLACKWOOD