1021 S HILTS AVE 90024
Certificate Information: 1021 S HILTS AVE 90024
- Application / Permit
- 22014-10000-02974
- Plan Check / Job No.
- B22LA11503
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL OF MASTER BATHROOM REMODEL OF KITCHEN PANTRY VARIOUS WINDOWS REPLACED/REMOVED/ADDED PER SCHEDULES CONVERT EXISTING WALK-IN AND BATHROOM INTO 2 NEW BATHROOMS
- Permit Issued
- Issued on 9/2/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 6/14/2023
Permit Application Status History
| Submitted | 6/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | NGHI SU |
| Corrections Issued | 7/6/2022 | NGHI SU |
| Quality Review Completed | 7/6/2022 | FARUK SEZER |
| Building Plans Picked Up | 7/7/2022 | APPLICANT |
| Applicant returned to address corrections | 7/15/2022 | TSE MING HUANG |
| Applicant returned to address corrections | 7/28/2022 | NGHI SU |
| Plan Check Approved | 9/2/2022 | NGHI SU |
| Issued | 9/2/2022 | APPLICANT |
| Permit Finaled | 6/14/2023 | STEPHANIE SWANSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/11/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2022 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 7/13/2022 | DINAH GARIN |
| Specific Plan | Cleared | 7/14/2022 | VALERIA CEJA |
| Grading Pre-Inspection | Cleared | 7/28/2022 | NGHI SU |
Contact Information
| Contractor | Willow Group Inc The; Lic. No.: 721043-B | 23974 CRAFTSMAN ROAD CALABASAS, CA 91302 |
| Engineer | Golabtounkar,, Tony Hamid; Lic. No.: C49104 | 1434 WESTWOOD BLVD ST 17 LOS ANGELES, CA 90024 |
| Engineer | Lycklama,, James Heinz; Lic. No.: L7525 | 32218 N BIG OAK LN CASTAIC, CA 91384 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/30/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 11/30/2022 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 11/30/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 12/1/2022 | Conditional Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 12/2/2022 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 12/2/2022 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 12/5/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 1/10/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/10/2023 | Approved | STEPHANIE SWANSON |
| Final | 1/10/2023 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 1/10/2023 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 1/10/2023 | Approved | STEPHANIE SWANSON |
| METHANE-Rough | 1/10/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/10/2023 | Approved | STEPHANIE SWANSON |
| Shower Pan | 1/12/2023 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 1/18/2023 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/20/2023 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 1/25/2023 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 1/25/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 6/9/2023 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 6/9/2023 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 6/9/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Final | 6/9/2023 | Approved | STEPHANIE SWANSON |
| Final | 6/9/2023 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 6/9/2023 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 6/9/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 6/9/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 6/9/2023 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 6/9/2023 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 6/9/2023 | Approved | STEPHANIE SWANSON |
| Final | 6/14/2023 | Permit Finaled | STEPHANIE SWANSON |