1021 S HILTS AVE 90024

Certificate Information: 1021 S HILTS AVE 90024

Application / Permit
22014-10000-02974
Plan Check / Job No.
B22LA11503
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF MASTER BATHROOM REMODEL OF KITCHEN PANTRY VARIOUS WINDOWS REPLACED/REMOVED/ADDED PER SCHEDULES CONVERT EXISTING WALK-IN AND BATHROOM INTO 2 NEW BATHROOMS
Permit Issued
Issued on 9/2/2022
Issuing Office
Metro
Current Status
Permit Finaled on 6/14/2023

Permit Application Status History

Submitted 6/14/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 NGHI SU
Corrections Issued 7/6/2022 NGHI SU
Quality Review Completed 7/6/2022 FARUK SEZER
Building Plans Picked Up 7/7/2022 APPLICANT
Applicant returned to address corrections 7/15/2022 TSE MING HUANG
Applicant returned to address corrections 7/28/2022 NGHI SU
Plan Check Approved 9/2/2022 NGHI SU
Issued 9/2/2022 APPLICANT
Permit Finaled 6/14/2023 STEPHANIE SWANSON

Permit Application Clearance Information

Sewer availability Cleared 7/11/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 7/13/2022 DINAH GARIN
Roof/Waste drainage to street Cleared 7/13/2022 DINAH GARIN
Specific Plan Cleared 7/14/2022 VALERIA CEJA
Grading Pre-Inspection Cleared 7/28/2022 NGHI SU

Contact Information

Contractor Willow Group Inc The; Lic. No.: 721043-B 23974 CRAFTSMAN ROAD      CALABASAS, CA 91302
Engineer Golabtounkar,, Tony Hamid; Lic. No.: C49104 1434 WESTWOOD BLVD ST 17      LOS ANGELES, CA 90024
Engineer Lycklama,, James Heinz; Lic. No.: L7525 32218 N BIG OAK LN      CASTAIC, CA 91384

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/30/2022 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 11/30/2022 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 11/30/2022 Corrections Issued CHRISTOPHER WILSON
Deputy Drilled-In Anchors 12/1/2022 Conditional Approval STEPHANIE SWANSON
Footing/Foundation/Slab 12/2/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 12/2/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 12/5/2022 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 1/10/2023 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 1/10/2023 Approved STEPHANIE SWANSON
Final 1/10/2023 Corrections Issued STEPHANIE SWANSON
Green Building Rough 1/10/2023 Partial Approval STEPHANIE SWANSON
HVAC-Rough 1/10/2023 Approved STEPHANIE SWANSON
METHANE-Rough 1/10/2023 Approved STEPHANIE SWANSON
PLUMBING-Rough 1/10/2023 Approved STEPHANIE SWANSON
Shower Pan 1/12/2023 Corrections Issued STEPHANIE SWANSON
Shower Pan 1/18/2023 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 1/20/2023 Approved STEPHANIE SWANSON
Drywall Nailing 1/25/2023 Corrections Issued STEPHANIE SWANSON
Green Building Rough 1/25/2023 Not Ready for Inspection STEPHANIE SWANSON
BUILDING-Rough-Frame 6/9/2023 Approved STEPHANIE SWANSON
Drywall Nailing 6/9/2023 Approved STEPHANIE SWANSON
Drywall Nailing 6/9/2023 Not Ready for Inspection STEPHANIE SWANSON
ELECTRICAL-Final 6/9/2023 Approved STEPHANIE SWANSON
Final 6/9/2023 Corrections Issued STEPHANIE SWANSON
Green Building Final 6/9/2023 Approved STEPHANIE SWANSON
Green Building Rough 6/9/2023 Approved STEPHANIE SWANSON
HVAC-Final 6/9/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 6/9/2023 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 6/9/2023 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 6/9/2023 Approved STEPHANIE SWANSON
Final 6/14/2023 Permit Finaled STEPHANIE SWANSON