922 S BURLINGTON AVE 1-36 90006
Certificate Information: 922 S BURLINGTON AVE 1-36 90006
- Application / Permit
- 22014-10000-02935
- Plan Check / Job No.
- B22LA11346
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- eplan convert storage space in (E) apartment to accessory dwelling unit - 420 sqft per CA Govt. Code 65852.2(e)(1)(C)
- Permit Issued
- Issued on 11/18/2022
- Issuing Office
- Current Status
- CofO Issued on 3/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 7/18/2022 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 7/20/2022 | CHARLES CHANG |
| Applicant returned to address corrections | 9/12/2022 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 9/16/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 11/2/2022 | FARSHAD ALIMOHAMADI |
| Issued | 11/18/2022 | APPLICANT |
| CofO in Progress | 3/4/2024 | JEROME BLACKWOOD |
| CofO Issued | 3/6/2024 | ERNESTO CORRAL |
| Permit Finaled | 3/6/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 7/25/2022 | MAX LODER |
| Address approval | Cleared | 7/26/2022 | CINDY QI |
| Sewer availability | Cleared | 7/26/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2022 | CINDY QI |
| Redevelopment Project Area | Cleared | 8/1/2022 | DAVID URITA |
| DAS Clearance | Cleared | 10/25/2022 | FARSHAD ALIMOHAMADI |
Contact Information
| Contractor | Adu Concepts; Lic. No.: 1018294-B | , |
| Contractor | Green Source Energy Inc; Lic. No.: 1018294-B | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 9/15/2023 | No Access for Inspection | RAMAZANALI ALMASI |
| Wood Frame | 9/21/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Insulation | 9/26/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Wood Frame | 9/26/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Insulation | 9/29/2023 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 9/29/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 10/5/2023 | Approved | JACOB MYERS |
| Drywall Nailing | 10/11/2023 | Approved | RAMAZANALI ALMASI |
| Final | 12/8/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 12/8/2023 | SGSOV Approved | JEROME BLACKWOOD |
| Smoke Detectors | 12/8/2023 | Approved | JEROME BLACKWOOD |
| Wood Frame | 12/8/2023 | Approved | JEROME BLACKWOOD |
| Final | 1/4/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Final | 1/17/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Final | 3/1/2024 | OK to Issue CofO | JEROME BLACKWOOD |