5312 S ST ANDREWS PL 90062
Certificate Information: 5312 S ST ANDREWS PL 90062
- Application / Permit
- 22014-10000-02922
- Plan Check / Job No.
- B22LA11332
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE AND STORAGE TO (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 7/13/2022
- Issuing Office
- Current Status
- CofO Issued on 9/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2022 | DANIEL YIP |
| Corrections Issued | 6/21/2022 | DANIEL YIP |
| Plan Check Approved | 7/12/2022 | DANIEL YIP |
| Issued | 7/13/2022 | APPLICANT |
| CofO in Progress | 9/25/2023 | DAVID FEILER |
| Permit Finaled | 9/25/2023 | DEROLD HAUFF |
| CofO Issued | 9/25/2023 | DEROLD HAUFF |
| Permit Finaled | 9/25/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/29/2022 | WALTER RAMIREZ |
| Address approval | Cleared | 7/5/2022 | CINDY QI |
| Sewer availability | Cleared | 7/5/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2022 | CINDY QI |
Contact Information
| Contractor | Bas Associates Construction; Lic. No.: 610162-B | , |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/19/2022 | Partial Approval | SABAS ALONSO |
| Sewer | 8/19/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 8/19/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 9/7/2022 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 9/14/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 10/11/2022 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 11/18/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Partial Approval | SABAS ALONSO |
| HVAC-Rough | 11/18/2022 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 11/18/2022 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 12/1/2022 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Wood Frame | 12/6/2022 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 12/16/2022 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 1/11/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 1/20/2023 | Approved | ALEJANDRO DE ARTOLA |
| Shower Pan | 1/20/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/20/2023 | No Access for Inspection | JOHN KIDWELL |
| Shower Pan | 3/20/2023 | No Access for Inspection | JOHN KIDWELL |
| Interior/Exterior Lathing | 3/23/2023 | Approved | SABAS ALONSO |
| Shower Pan | 3/23/2023 | Partial Approval | SABAS ALONSO |
| Shower Pan | 4/26/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 8/1/2023 | Approved | SABAS ALONSO |
| Final | 8/1/2023 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/1/2023 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 8/1/2023 | Approved | SABAS ALONSO |
| Final | 8/25/2023 | Not Ready for Inspection | SABAS ALONSO |
| Final | 8/30/2023 | Not Ready for Inspection | SABAS ALONSO |
| Final | 9/12/2023 | Corrections Issued | SABAS ALONSO |
| Final | 9/19/2023 | OK to Issue CofO | SABAS ALONSO |