Pre-Inspection
|
2/24/2025
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Excavation/Setback/Form/Re-Bar
|
6/20/2025
|
Partial Approval
|
DAVID TSAU
|
|
Pre-Inspection
|
7/1/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Excavation/Setback/Form/Re-Bar
|
7/29/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Light Gage Steel Frame
|
8/6/2025
|
Partial Inspection
|
MICHAEL PETRUSKO
|
|
Green Building Rough
|
9/8/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Reinforced Concrete Frame
|
9/8/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Reinforced Masonry Frame
|
9/8/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Excavation/Setback/Form/Re-Bar
|
9/11/2025
|
Approved
|
MICHAEL PETRUSKO
|
|
Pre-Inspection
|
9/18/2025
|
Partial Inspection
|
MICHAEL PETRUSKO
|
|
Pre-Inspection
|
9/25/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/28/2025
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Light Gage Steel Frame
|
10/29/2025
|
Approved
|
MICHAEL PETRUSKO
|
|
Deputy Drilled-In Anchors
|
11/7/2025
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Special/Order Compliance
|
11/12/2025
|
Partial Inspection
|
MICHAEL PETRUSKO
|
|
Green Building Rough
|
11/14/2025
|
Not Ready for Inspection
|
RICARDO ROBLES
|
|
Reinforced Concrete Frame
|
11/14/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Green Building Rough
|
11/21/2025
|
Approved
|
MICHAEL PETRUSKO
|
|
Reinforced Concrete Frame
|
11/21/2025
|
Approved
|
MICHAEL PETRUSKO
|
|
Excavation/Setback/Form/Re-Bar
|
11/24/2025
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Deputy Reinf. Concrete
|
11/25/2025
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Excavation/Setback/Form/Re-Bar
|
12/16/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Deputy Drilled-In Anchors
|
12/17/2025
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Excavation/Setback/Form/Re-Bar
|
12/17/2025
|
Conditional Approval
|
RICARDO ROBLES
|
|
Deputy Reinf. Concrete
|
12/18/2025
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Deputy Steel/Welding
|
12/18/2025
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Excavation/Setback/Form/Re-Bar
|
12/18/2025
|
Approved
|
MICHAEL PETRUSKO
|
|
Deputy Steel/Welding
|
12/19/2025
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Light Gage Steel Frame
|
12/19/2025
|
Approved
|
MICHAEL PETRUSKO
|
|
Light Gage Steel Frame
|
12/22/2025
|
Approved
|
MICHAEL PETRUSKO
|
|
Deputy Reinf. Concrete
|
12/23/2025
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Excavation/Setback/Form/Re-Bar
|
12/24/2025
|
Partial Approval
|
MICHAEL PETRUSKO
|
|
Deputy Reinf. Concrete
|
12/30/2025
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Excavation/Setback/Form/Re-Bar
|
12/30/2025
|
Approved
|
MICHAEL PETRUSKO
|
|
Deputy Shotcrete
|
12/31/2025
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Excavation/Setback/Form/Re-Bar
|
12/31/2025
|
Approved
|
MICHAEL PETRUSKO
|
|
Deputy Shotcrete
|
1/6/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Deputy Steel/Welding
|
1/6/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Deputy Drilled-In Anchors
|
1/13/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Deputy Steel/Welding
|
1/13/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Deputy Drilled-In Anchors
|
1/15/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Drywall Nailing
|
1/26/2026
|
Partial Approval
|
DAVID TSAU
|
|
Light Gage Steel Frame
|
1/26/2026
|
Partial Approval
|
DAVID TSAU
|
|
Deputy Steel/Welding
|
1/29/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Light Gage Steel Frame
|
1/30/2026
|
Partial Approval
|
MICHAEL PETRUSKO
|
|
Deputy Drilled-In Anchors
|
2/17/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Deputy Drilled-In Anchors
|
2/25/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Deputy Reinf. Concrete
|
2/26/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Excavation/Setback/Form/Re-Bar
|
2/26/2026
|
Partial Inspection
|
MICHAEL PETRUSKO
|
|
Deputy Drilled-In Anchors
|
3/9/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Deputy Steel/Welding
|
3/10/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Grading Pre-Inspection
|
3/16/2026
|
Partial Approval
|
MICHAEL PETRUSKO
|
|
Deputy Drilled-In Anchors
|
3/25/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Drywall Nailing
|
4/3/2026
|
Partial Approval
|
MICHAEL PETRUSKO
|
|
Light Gage Steel Frame
|
4/3/2026
|
Partial Approval
|
MICHAEL PETRUSKO
|
|
Deputy Drilled-In Anchors
|
4/7/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Deputy Steel/Welding
|
4/7/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Excavation/Setback/Form/Re-Bar
|
4/7/2026
|
Approved
|
MICHAEL PETRUSKO
|
|
Deputy Drilled-In Anchors
|
4/9/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Deputy Steel/Welding
|
4/9/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Deputy Steel/Welding
|
4/10/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Deputy Drilled-In Anchors
|
4/14/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Deputy Reinf. Concrete
|
4/16/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Excavation/Setback/Form/Re-Bar
|
4/16/2026
|
Approved
|
MICHAEL PETRUSKO
|
|
Deputy Reinf. Concrete
|
4/21/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Light Gage Steel Frame
|
4/22/2026
|
Partial Approval
|
MICHAEL PETRUSKO
|
|
Pre-Inspection
|
4/22/2026
|
Partial Inspection
|
DAVID TSAU
|
|
Deputy Drilled-In Anchors
|
4/28/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Deputy Reinf. Concrete
|
4/30/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Deputy Steel/Welding
|
5/14/2026
|
Conditional Approval
|
MICHAEL PETRUSKO
|
|
Interior/Exterior Lathing
|
5/15/2026
|
Approved
|
MICHAEL PETRUSKO
|
|
Drywall Nailing
|
5/20/2026
|
Approved
|
MICHAEL PETRUSKO
|
|
Drywall Nailing
|
5/29/2026
|
Approved
|
MICHAEL PETRUSKO
|