4506 N GREENBUSH AVE 91423

Certificate Information: 4506 N GREENBUSH AVE 91423

Application / Permit
22014-10000-02901
Plan Check / Job No.
B22LA11264
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan ADDITION AND REMODELING TO (E) SFD
Permit Issued
Issued on 10/11/2022
Issuing Office
Current Status
CofO Issued on 10/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 ADRIANA LOPEZ
Corrections Issued 7/9/2022 ADRIANA LOPEZ
Quality Review Completed 7/19/2022 GARO TELMI
Plan Check Approved 10/3/2022 ADRIANA LOPEZ
Issued 10/11/2022 APPLICANT
CofO in Progress 9/18/2024 MISAEL ESPARZA
CofO Issued 10/1/2024 DANIEL ORRANTE
Permit Finaled 10/1/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/29/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 8/1/2022 ROMAN GUTIERREZ
Sewer availability Cleared 8/1/2022 ROMAN GUTIERREZ
ZI Cleared 8/9/2022 DANG NGUYEN

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/7/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 11/15/2023 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 11/22/2023 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/7/2023 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 12/7/2023 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/28/2023 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 1/18/2024 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/9/2024 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 2/23/2024 Corrections Issued MISAEL ESPARZA
HVAC-Rough 2/23/2024 Approved MISAEL ESPARZA
ELECTRICAL-Rough 3/6/2024 Approved MISAEL ESPARZA
PLUMBING-Rough 3/6/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 3/13/2024 Corrections Issued MISAEL ESPARZA
Green Building Rough 3/13/2024 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 3/13/2024 Not Ready for Inspection MISAEL ESPARZA
Deputy Wood Construction 3/14/2024 Conditional Approval JUAN VALENZUELA
Shower Pan 3/15/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 3/22/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/22/2024 Partial Approval MISAEL ESPARZA
Insulation 4/2/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/2/2024 Approved MISAEL ESPARZA
Drywall Nailing 4/9/2024 Approved MISAEL ESPARZA
Green Building Rough 4/9/2024 Approved MISAEL ESPARZA
Gas Test 5/31/2024 Approved MISAEL ESPARZA
ELECTRICAL-Final 9/3/2024 Corrections Issued MISAEL ESPARZA
HVAC-Final 9/3/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 9/3/2024 Approved MISAEL ESPARZA
ELECTRICAL-Final 9/9/2024 Approved MISAEL ESPARZA
HVAC-Final 9/9/2024 Approved MISAEL ESPARZA
Service/Power Release 9/11/2024 Approved MISAEL ESPARZA
Final 9/17/2024 OK to Issue CofO MISAEL ESPARZA
Green Building Final 9/17/2024 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/17/2024 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 9/17/2024 Approved MISAEL ESPARZA